Project Update
The Venetian Causeway water and sewer main upgrades continue to progress. The project team will be working on multiple segments concurrently.
Schedule
-
The contractor will be completing valve installations beneath Venetian Way along San Marco Island. Work is expected to be ongoing through end of May 2026.
Work hours
The contractor will continue daily operations from 7 a.m. to 6 p.m., Monday through Friday. Substantial completion of the project is anticipated in late spring to early summer 2026, with final completion expected by late summer 2026. Between substantial and final completion, the community may experience minor road closures associated with final project operations.
The above noted schedule and work hours are subject to change due to weather and/or other unforeseen circumstances.
Traffic Impacts
The City remains committed to minimizing disruption for residents and visitors. Traffic operations will be assisted by off-duty officers and flaggers during peak traffic hours. Please find the detour route information below:
San Marco Island Detour
Traveling west along Venetian Way/Causeway (approaching N Venetian Way)
- Proceed west along Venetian Way/Venetian Causeway until the roadway junction and bare right onto the right-hand junction/fork of N Venetian Way.
- Proceed along the right-hand junction/fork until you reach the stop sign, then continue into the main N Venetian Way through road.
Traveling east along Venetian Way/Causeway (approaching San Marino Island)
- Eastbound traffic along Venetian Way at San Marco Island will not be impacted.
|