Project Update: San Marco Island to San Marino Island
The Venetian Causeway water and sewer main upgrades will be moving into the next section of the corridor. The construction between Belle Isle and Dade Boulevard is entering the final phase of the horizontal directional drilling operation, where the pipe will be pulled back through the bore into its final position. This work will require continuous contractor presence, including an overnight shift from 6 p.m. on Tuesday, November 19, 2024, to 12 p.m. on Wednesday, November 20, 2024. Please note that some noise may be generated during this operation.
The drilling, installation, and testing of the new water main between Belle Isle and Dade Blvd are expected to be completed within the next 3 to 4 weeks. The new HDPE pipe is scheduled to be fused and pulled into the borehole by the end of next week, followed by surveying, pressure testing, and temporary road restoration activities.
|