Project Updates: Fire Flow Packages

Notice Date: August 16, 2026

What’s Happening

Please be advised of the following upcoming construction activities and associated parking and traffic impacts in your area:


Monday, August 17 through Friday, September 4, the Fire Flow Package (FFP) contractors will continue water main installation, asphalt trench restoration, sidewalk restoration and road base installation. The first lift of asphalt will be placed to reduce dust impacts, followed by a final surface course upon project completion for a unified roadway finish. Work will occur in the following areas: 


Fire Flow Package 1 

  • North and south sidewalks at Michigan Court and 6 Street (week of August 17)
  • North and south sidewalks at Michigan Court and 7 Street (week of August 17)
  • North and south sidewalks at Lenox Court and 7 Street (week of August 17)
  • South sidewalk at Michigan Court and 8 Street (week of August 17)
  • 14 Street between Michigan Court and Lenox Court (ongoing)

 

Fire Flow Package 2

  • 14 Street, Pennsylvania Avenue to Euclid Avenue (ongoing)
  • 14 Street, Euclid Avenue to Meridian Avenue (starting late August)
  • 17 Street, east of Collins Avenue (ongoing)
  • 18 Street, east of Collins Avenue (ongoing)

Water Main Testing Notice

Testing of the newly installed water main is ongoing throughout the project area. You may notice small taps of running water. Please do not touch, turn off or tamper with these taps. These tests are required by the Florida Department of Health and must run their full course without interruption. If stopped, the contractors would need to restart the process, which would cause delays. This testing is an important step to ensure the water system is safe and ready for use. Once the testing period is over, construction crews are able to connect the newly installed water mains to the city system. We appreciate your cooperation and patience. Please refer to the maps below for location details.

Projects Overview

The FFPs are critical infrastructure upgrade projects, designed to improve the reliability and safety of the local water distribution system. The projects include upsizing existing water mains and installing new water connections to address areas that currently do not meet required fire flow standards.


Benefits

  • Improved fire protection and public safety
  • Increased system capacity and reliability
  • Upgraded water mains and connections (some of the existing lines have been in place since the 1940s and 1950s)
  • Enhanced infrastructure to support future growth


Sidewalk Restoration: Please expect temporary sidewalk closures and restricted parking at the locations below for up to 24 hours while the concrete cures. Access to residences will be maintained and coordinated with construction crews to minimize impacts.

FFP1: Please refer to the map above for additional details.

FFP2: Please refer to the map below for additional details.

Please be advised that temporary parking restrictions will be in effect due to ongoing infrastructure improvement work. Parking will be prohibited Monday through Sunday within the designated work zones. Parking spaces will be restored and reopened as construction activities are completed in each area. 


Construction Timeline

Construction is ongoing Mondays through Fridays from 7:30 a.m. until 6 p.m. unless otherwise noted. Any extended work hours or weekend work required is subject to city approval and community notification.


What to Expect

  • Moderate levels of construction noise are expected during work hours.
  • Equipment and container storage will be limited to designated areas.
  • Machinery and workers will be present on the job site. Residents are advised to use caution when crews are present and to follow all posted signage.
  • Pedestrian and traffic detours will be implemented as needed for safety.
  • All efforts are being made to minimize impacts to area residents and businesses.
  • Restoration activities will take place upon the project’s completion and will address areas impacted by the construction.
  • If you have a private parking space that you cannot access during construction, please contact us with your vehicle details (make, model, color, tag) to make arrangements for alternate parking during construction.
  • Construction crews will assist with sanitation services, trash pick-up as needed while the work zones are active.
  • Work schedule may change due to inclement weather or unexpected conditions.


Updates with the scheduled working locations will be provided throughout the project. To join the project email list, please contact the public information team at the number or email below. We thank you for your patience as the city completes these necessary infrastructure upgrades.

Who to Contact

For information about the project, please call / text Public Information Liaison 
Dayana Sanjurjo at 786.239.8862 or
email at dsanjurjo@mrgmiami.com.

To learn more about the city’s projects and innovative initiatives, visit www.miamibeachfl.gov/NAD.


To request this material in alternate format, sign language interpreter (5-day notice required), information on access for persons with disabilities, and/or any accommodation to review any document or participate in any city-sponsored proceedings, call 305.604.2ADA (2232) (voice), select 1 (English) or 2 (Spanish) and leave a message with your request. TTY users may call via 711 (Florida Relay Service). You can also make requests online at www.miamibeachfl.gov/ada by selecting ADA request.

Facebook  X  Instagram