Project Updates: Fire Flow Packages

Notice Date: March 21, 2026

What’s Happening

Please be advised of the following upcoming construction activities and associated parking and traffic impacts in your area:


Monday, Mar. 23 through Monday, Apr. 13, the Fire Flow Package (FFP) contractors will continue water main installation and perform restoration work in the following areas:

  • 10 Street between Alton Rd. and Meridan Ave.
  • 20 Street east of Collins Ave.

 

Note: nighttime construction work on 20 St. east of Collins Ave. is scheduled to begin on Monday, March 30, and is expected to continue for approximately three weeks.

 

Nighttime Construction Schedule:

  • Monday – Friday: 7 p.m. to 5:30 a.m.

 

A noise waiver permit has been issued by the city, and all necessary measures will be implemented to minimize impacts to nearby businesses and residents.


Water Main Testing Notice

Testing of the newly installed water main is ongoing throughout the project area. You may notice small taps of running water. Please do not touch, turn off or tamper with these taps. These tests are required by the Florida Department of Health and must run their full course without interruption. If stopped, the contractors (Amici Engineering Contractors and Metro Equipment Service. Inc) would need to restart the process, which would cause delays. This testing is an important step to ensure the water system is safe and ready for use. We appreciate your cooperation and patience while it is completed. Please refer to the maps below for location details.  

Projects Overview

The FFPs are critical infrastructure upgrade projects, designed to enhance the reliability and safety of the local water distribution system. The projects include upsizing existing water mains and installing new water connections to address areas that currently do not meet required fire flow standards.

Benefits

  • Improved fire protection and public safety
  • Increased system capacity and reliability
  • Upgraded water mains and connections (some of the existing lines have been in place since the 1940s and 1950s)
  • Enhanced infrastructure to support future growth


Please be advised:

For FFP 1, parking will be temporarily unavailable on the south side of 10 Street, between Michigan Ave. and Jefferson Ave. from March 14 through March 27 due to ongoing infrastructure work. Parking will be prohibited Monday through Sunday. Please see map herein (above) for details on the impacted parking area.

 

For FFP 2, parking will be temporarily unavailable on both sides of 20 Street, east of Collins Ave., due to ongoing infrastructure work. Parking will be prohibited Monday through Sunday. Please see map herein (below) for details on the impacted parking area.

 

In addition to the parking restrictions, full road closures will also be implemented at times in these areas. Drivers are encouraged to use alternate routes around the work zones and follow all posted detour signs.

 

These restrictions are necessary to facilitate essential improvements and ensure public safety. All individuals are encouraged to seek alternate parking and adhere to posted signage to avoid enforcement measures.

Construction Timeline

Construction work is ongoing, Mondays through Fridays. Work hours range from 7:30 a.m. until 6 p.m. Any extended work hours or weekend work required is subject to city approval and community notification.


What to Expect

  • Moderate levels of construction noise are expected during the day.
  • Equipment and container storage will be limited to designated areas.
  • Machinery and workers will be present on the job site. Residents are advised to use caution when crews are present and to follow all posted signage.
  • Pedestrian and traffic detours will be implemented as needed for safety.
  • All efforts are being made to minimize impacts to area residents and businesses.
  • Restoration activities will take place upon the project’s completion and will address areas impacted by the construction.
  • If you have a private parking space that you cannot access during construction, please contact us with your vehicle details (make, model, color, tag) to make arrangements for alternate parking during construction.
  • Work schedule may change due to inclement weather or unexpected conditions.


Updates with the scheduled working locations will be provided throughout the project. To join the project email list, please contact the public information team - details below.


We thank you for your patience as the city works on this necessary infrastructure upgrade.

Who to Contact

For information about the project, please call / text Public Information Liaison, 
Dayana Sanjurjo at 786.239.8862 or
email at dsanjurjo@mrgmiami.com

To learn more about the city’s projects and innovative initiatives, visit www.miamibeachfl.gov/NAD.


To request this material in alternate format, sign language interpreter (5-day notice required), information on access for persons with disabilities, and/or any accommodation to review any document or participate in any city-sponsored proceedings, call 305.604.2ADA (2232) (voice), select 1 (English) or 2 (Spanish) and leave a message with your request. TTY users may call via 711 (Florida Relay Service). You can also make requests online at www.miamibeachfl.gov/ada by selecting ADA request.

Facebook  X  Instagram