What’s Happening

Please be advised of the following upcoming construction activities and associated parking and traffic impacts in your area:


Monday, May 18 through Friday, June 29, The Fire Flow Package (FFP) contractors will continue water main installation, asphalt trench restoration, and road base installation. The first lift of asphalt will be placed to reduce dust impacts, followed by a final resurfacing upon project completion for a unified roadway finish. Work will occur in the following areas:

 

Fire Flow Package 1 

  • 10 Street, Pennsylvania Ct. to Washington Ave. (ongoing until May. 29)
  • 13 Street, Alton Rd. to Michigan Ave. (Jun. 8 – Jun. 29)
  • 14 Street, Alton Rd. to Michigan Ct. (Jun. 8 – Jun. 29)
  • Michigan Ct., 14 Street to 13 Street (Jun. 8 – Jun. 29)

 

Fire Flow Package 2

  • 14 Place, Meridian Ave. to Euclid Ave. (ongoing until May 27)
  • 14 Place, Euclid Ave. to Pennsylvania Ave. (Jun. 1 – Jun. 26)
  • 20 Street east of Collins Ave. (ongoing until Jun. 12)

 

Nighttime construction on 20 Street will continue for approximately four weeks, Monday through Friday from 9 p.m. to 5:30 a.m.

 

Sidewalks and curb concrete repair work continues in the following area listed below. Please expect sidewalks closures and restricted parking for a full 24-hours as the concrete dries. Access to residences will be coordinated with construction crews.

 

  • 12 Street, Meridan Ave. to Pennsylvania Ave. (ongoing until May 27)

Water Main Testing Notice

Testing of the newly installed water main is ongoing and requires small taps of running water. Please do not touch, turn off or tamper with these taps. These tests are required by the Florida Department of Health and must run their full course without interruption. If stopped, the contractors (Amici Engineering Contractors and Metro Equipment Service. Inc) would need to restart the process, which would cause delays. This testing is an important step to ensure the water system is safe and ready for use. Please refer to the maps below for location details.  

Projects Overview

The FFPs are critical infrastructure upgrade projects, designed to enhance the reliability and safety of the local water distribution system. The projects include upsizing existing water mains and installing new water connections to address areas that currently do not meet required fire flow standards.


Benefits

  • Improved fire protection and public safety
  • Increased system capacity and reliability
  • Upgraded water mains and connections (some of the existing lines have been in place since the 1940s and 1950s)
  • Enhanced infrastructure to support future growth

Please be advised that temporary parking restrictions will be in effect due to ongoing infrastructure improvement work. Parking will be prohibited Monday through Sunday within the designated work zones. Parking spaces will be restored and reopened as construction activities are completed in each area. 


FFP1: Please refer to the map of 10 St. (above) for additional details.

 

FFP2: Please refer to the maps (below) of 14 Place and 20 St. for additional details.

Construction Timeline

Construction work is ongoing, Mondays through Fridays. Work hours range from 7:30 a.m. until 6 p.m. (unless otherwise stated). Any extended work hours or weekend work required is subject to city approval and community notification.


What to Expect

  • Moderate levels of construction noise are expected during the day.
  • Equipment and container storage will be limited to designated areas.
  • Machinery and workers will be present on the job site. Residents are advised to use caution when crews are present and to follow all posted signage.
  • Pedestrian and traffic detours will be implemented as needed for safety.
  • All efforts are being made to minimize impacts to area residents and businesses.
  • Restoration activities will take place upon the project’s completion and will address areas impacted by the construction.
  • If you have a private parking space that you cannot access during construction, please contact us with your vehicle details (make, model, color, tag) to make arrangements for alternate parking during construction.
  • Work schedule may change due to inclement weather or unexpected conditions.


Updates with the scheduled working locations will be provided throughout the project. To join the project email list, please contact the public information team - details below.


We thank you for your patience as the city works on this necessary infrastructure upgrade.

Who to Contact

For information about the project, please call / text Public Information Liaison, 
Dayana Sanjurjo at 786.239.8862 or
email at dsanjurjo@mrgmiami.com

To learn more about the city’s projects and innovative initiatives, visit www.miamibeachfl.gov/NAD.


To request this material in alternate format, sign language interpreter (5-day notice required), information on access for persons with disabilities, and/or any accommodation to review any document or participate in any city-sponsored proceedings, call 305.604.2ADA (2232) (voice), select 1 (English) or 2 (Spanish) and leave a message with your request. TTY users may call via 711 (Florida Relay Service). You can also make requests online at www.miamibeachfl.gov/ada by selecting ADA request.

Facebook  X  Instagram