Clairemont, Bay Park and Morena
Progress on the Morena Pump Station continues. Crews worked on the upper levels of the pump station by continuing construction of the electrical building, maintenance building, and the perimeter walls, as well continuing progress on the various structures that will form the future pump station.
More than 11 miles of pipeline have been installed as part of the Morena Conveyance South and Middle and Bike Lanes project. Crews are currently working at the intersection of Clairemont Mesa Boulevard and Genesee Avenue, installing pipeline during nighttime hours from 9 p.m. to 5 a.m. Additional pipeline installation is also underway along West Morena Boulevard.
Recently, crews completed curb-to-curb paving and applied new roadway striping on Clairemont Drive. Paving operations along Clairemont Drive are expected to resume in early 2026, progressing north through the intersection of Clairemont Mesa Boulevard and Genesee Avenue. Looking ahead, crews are preparing for the pipeline tie-in at Genesee Avenue and Appleton Street, which will connect the Morena Conveyance Middle pipeline with the Northern alignment.
|