CONSTRUCTION ACTIVITIES - Week of April 5
With construction on the 9-mile Arrow corridor almost 90% complete and bridge construction almost 100% complete, crews are installing pedestrian swing gates and railings at the grade crossings; paving and reconstructing curbs, gutters, and sidewalks; installing perimeter fencing along the corridor; completing the installation of underground utilities and drainage systems; surfacing and leveling the track; and preparing for train testing.

  • Crews continue to work on Park Avenue improvements Monday through Friday 24 hours/day. A local detour is posted and sends traffic north around Sylvan Park.
  • Intermittent daytime (7:00 a.m. to 3:00 p.m.) lane closures will occur on local streets including E Street, Waterman Avenue, Tippecanoe Avenue, California Street, New York Street, Tennessee Street, Eureka Street, and Church Street. Through travel/two-way travel will remain at all times at each location.
  • Beginning mid-April crews will start installing a concrete drainage structure at Tippecanoe Avenue. This work will require full closures at the rail crossing. Additional information will be provided including closure dates and detours.

Crews are preparing the corridor for train testing.

  • Pre-testing of the roadway gates at the rail crossings will begin Monday, April 5 and will continue through Friday, April 16, from 7:00 a.m. to 3:00 p.m. each day. Flaggers will be present to assist traffic through the rail crossings. Please expect one to three minute delays at the crossings during this time.
  • Rail grinding will continue through Friday, April 9, from 7:00 a.m. to 3:00 p.m. each day. A hi-rail truck traveling at approximately 3mph will travel along the mainline. Flaggers will be present to assist the hi-rail truck through the rail crossings. There will be delays of up to one minute at each crossing as the hi-rail truck passes through.

At times, work throughout the corridor may be loud and cause vibration. Please remember construction is dynamic and the schedule is subject to change.
Crews working on the pedestrian crossing and sidewalk at the downtown Redlands station.
Crews working on surfacing the railroad track between Richardson and Mountain View.
ADJACENT PROJECTS
Inland Valley Development Agency (IVDA) Mountain View Avenue Utility Work
Mountain View Avenue is closed through mid-2021 between Victoria Avenue and Coulston Street for various utility work unrelated to the Redlands Passenger Rail Project. The work includes the relocation of high pressure gas, water, and sewer lines as part of an overall widening of Mountain View Avenue from I-10 to the San Bernardino International Airport. Please click here for the detour map and more information.
ABOUT THE ARROW PROJECT
The Arrow is scheduled to begin service in early 2022 and will run between the San Bernardino Transit Center located at Rialto Avenue and E Street in Downtown San Bernardino adjacent to San Manuel Stadium and will terminate at the University of Redlands. The regional rail service will integrate with other modes of transportation such as cars, buses, and bicycles and will offer residents, businesses, and visitors a new option for live, work, and play.
 
If you would like to receive construction alerts via text messages, text RedlandsArrow to 31996. Reply STOP to cancel, text HELP for help. Normal text and data message rates may apply.

Si prefiere recibir información de construcción en español, llame al (877) 55 - SBCTA.