Reminder: G.O. Bond Bayshore Traffic Calming

Notice Date: Friday, October 30, 2026

 

What’s Happening

Beginning the week of November 2, 2026, the City will begin installing traffic-calming improvements throughout the Bayshore neighborhood. Planned enhancements include a combination of speed tables, speed cushions, traffic circles and intersection improvements.



These measures are intended to improve neighborhood safety by reducing vehicle speeds and discouraging cut-through traffic on local streets.


Residents whose properties are adjacent to a proposed traffic-calming device should have received a door hanger from the City providing notice of the upcoming construction work.


Phase 1

  • Start: Week of November 2, 2026
  • Location: N Meridian Avenue between Dade Blvd and W 28 St
  • Improvements: Two speed tables


Details regarding the next phases and construction schedules for the remaining locations will be shared in future project notices. Below is a quick overview of where improvements will occur:

Location

Improvement Type

N Meridian Avenue between Dade Boulevard and W 28 Street

Two (2) speed tables

W 28 Street between Meridian Avenue and Royal Palm Avenue

Three (3) speed tables

Prairie Avenue between Dade Boulevard and W 28 Street

Three (3) speed tables

Prairie Avenue between W 28 Street and W 34 Street

Two (2) speed tables and one (1) traffic circle

Royal Palm Avenue between W 31 Street and W 40 Street

Three (3) speed tables

Sheridan Avenue between W 28 Street and W 37 Street

Two (2) speed tables and two (2) traffic circles

Chase Avenue between Alton Rd and W 40 Street

Three (3) speed tables and one (1) intersection improvement

Timeline

This project is anticipated to begin the week of November 2, 2026 and take approximately 7 months to complete. Work hours are Monday–Friday from 8 a.m. to 5 p.m.


Please know that this schedule may change due to weather and/or other unforeseen circumstances.


What to Expect

  • Construction equipment and workers will be present in the area.
  • Resident access to properties will be maintained at all times during construction.
  • Pedestrian access will be maintained at all times.
  • Traffic patterns may change due to temporary closures and detours.
  • Temporary parking restrictions will be in place and enforced. Please follow all posted signage.

Contact

To explore the project’s history and previous updates, please visit our project page for more details.


For more information, please contact Mid Beach Neighborhood Affairs Coordinator Gabriella Gonzalez at GabriellaGonzalez@miamibeachfl.gov.

To learn more about the city’s projects and innovative initiatives, visit www.miamibeachfl.gov/NAD.


To request this material in alternate format, sign language interpreter (5-day notice required), information on access for persons with disabilities, and/or any accommodation to review any document or participate in any city-sponsored proceedings, call 305.604.2ADA (2232) (voice), select 1 (English) or 2 (Spanish) and leave a message with your request. TTY users may call via 711 (Florida Relay Service). You can also make requests online at www.miamibeachfl.gov/ada by selecting ADA request.