GEV - Milling and Paving Dates

Golden Eagle Village Owners,


Starting Wednesday, July 17, MR Tanner will begin milling/ removing the Asphalt sections of your village roadways. They will not be removing or working on the decorative concrete.


The following week, on July 25, MR Tanner will begin paving the green section of the road as marked on the map below.

See below for access planning for July 17 and July 25. Please read the information below, and the project notice provided by Frank Civil Consulting so you are fully prepared for the paving day on July 25.


Please contact the Association office if you have any questions,


Alex Wright, CMCA, CAAM

Interim Community Manager, Superstition Mountain


*Click the map below for a full-sized PDF of the 2024 Project Map.

July 17 - Milling

Access will not be restricted completely during the milling process. However, due to the tight nature of the roads in your Village, entering or exiting during the process may be met with delays while the equipment is in the road.


MR Tanner anticipates starting the day milling southbound SMD (purple) and then moving to Golden Eagle (green). This means localized delays are more likely in the afternoon of the 17th.


July 25 - Paving

Access will be restricted entirely for 24 hours beginning the morning of July 25 through the morning of July 26 (assuming no weather delays). During this time, vehicular access into and out of the village will be completely blocked. 


To facilitate residential access during this 24-hour time frame, the Golf Club is allowing Golden Eagle Residents to park in the Golf Club parking lot. Alternatively, you may park in the cul-de-sac across SMD in Juniper Village. Both areas are a short walk. If you have any questions or concerns about this process, please let me know as soon as possible.


Parking

If you are planning to be on property on July 25 AND need to enter or exit in your vehicle when access is restricted in your village, please plan ahead to park in one of the designated locations. Because access restrictions begin at 6:00 am, you will want to park your vehicle at the Golf Club the night prior – Wednesday, July 24.

Schedule

What Comes Next?


  • 7/17 - 7/19: Pavement Removal (no closure, but delays expected, driving over dirt allowed)             


  • 7/22 - 7/30: Ground Prep & Grading Work (no closure, driving over dirt allowed)     


  • 7/25: Phase 1 Asphalt Paving - Golden Eagle Village
  • (Green Section of Map closed 6am to 6am)


  • 7/26: Phase 2 Asphalt Paving - First Water Village
  • (Blue Section of Map closed 6am to 6am)   


  • 7/31: Phase 3 Asphalt Paving - Lost Gold Estates
  • (Yellow Section of Map closed 6am to 6am) 


  • 8/1: Phase 4 Asphalt Paving - SMD - Prospector Village Impacted
  • (Red Section of Map closed 6am to 6am) 


  • 8/2: Phase 5 Asphalt Paving - SMD - Sunset, Greythorn, Wildflower Impacted
  • (Purple Section of Map closed 6am to 6am) 


  • TBD: Re Stripe Lines (No closure, open to traffic)    

                                               

  • 8/12 - 8/16: Utility Collar Raising (No closure, open to traffic)      


*The schedule is subject to change due to inclement weather or other unforeseen circumstances. Any changes will be communicated via email blast.             

FAQs

What Comes Next?


  • 7/17 - 7/19: Pavement Removal (no closure, but delays expected, driving over dirt allowed)             


  • 7/22 - 7/30: Ground Prep & Grading Work (no closure, driving over dirt allowed)     


  • 7/25: Phase 1 Asphalt Paving - Golden Eagle Village
  • (Green Section of Map closed 6am to 6am)


  • 7/26: Phase 2 Asphalt Paving - First Water Village
  • (Blue Section of Map closed 6am to 6am)   


  • 7/31: Phase 3 Asphalt Paving - Lost Gold Estates
  • (Yellow Section of Map closed 6am to 6am) 


  • 8/1: Phase 4 Asphalt Paving - SMD - Prospector Village Impacted
  • (Red Section of Map closed 6am to 6am) 


  • 8/2: Phase 5 Asphalt Paving - SMD - Sunset, Greythorn, Wildflower Impacted
  • (Purple Section of Map closed 6am to 6am) 


  • TBD: Re Stripe Lines (No closure, open to traffic)    

                                               

  • 8/12 - 8/16: Utility Collar Raising (No closure, open to traffic)      


*The schedule is subject to change due to inclement weather or other unforeseen circumstances. Any changes will be communicated via email blast.             

Resources & Communications

6.30.24 | Road Work - Announcement Email Blast
7.11.24 | Road Update 2 - Milling Begins Next Week!
2024 Road Work | Projects Tab on Community Website
Community Notice - MR Tanner, Frank Civil Consulting
Superstition Mountain is proudly and professionally managed by
Contact Information

Association Office: 480-983-6773
Gate Staff: Superstition.Mountain@CoveySecurity.com 480-983-9270