There are several projects underway in Chino. Many of these projects have been in the works for years and once completed, will bring much needed improvements to our community.


We appreciate your patience as you navigate the inconvenience of detours and road closures. Remember to plan ahead and follow posted signage and detours.

City Road Improvements

Central, D Street & Dupont Water Main Replacement Projects


Project Description:

The city is actively engaged in Water Main Replacement projects, a vital component of our comprehensive Capital Improvement Program. The goal is to enhance water services and increase the durability of the main water line for Central Avenue businesses.


Impacted Areas:

  • Central Avenue: Chino Avenue to C Street.
  • D Street: Central Avenue to 6th Street.
  • Dupont Avenue: Gates Street to Alton Street.


Timeline: 

This phase of the project is completed, the next phase will resume in 2024.


Edison Avenue Widening Project


Landscaping and Street light work will be on going through the New Year. Once completed Edison Avenue will be repaved. Construction of street improvement at Edison Avenue and Oaks Avenue is still outstanding and will continue in early 2024.


Impacts:

During construction, lane closures are to be expects along Central Avenue and Edison Avenue. Construction will also include the modification of the traffic signals along Edison Avenue at Central Avenue, 12th Street and Oaks Avenue. This work will temporarily impact the operation of the traffic signals causing delays until the work is completed. Expect longer travel times through the area, use of alternative routes is recommended.


Timeline:

Winter 2024.


Detour Information:

Access YMCA via 12th entrance on Edison Avenue or from College Park Avenue.


More About the Project:

Construction of storm drain, street widening, curb, gutter & sidewalk, pavement rehabilitation, Ayala Park entrance improvements, traffic signal improvements, and pedestrian accessibility improvements as part of the College Park ultimate Improvement Project.


Merrill Avenue from Euclid Avenue to Carpenter Avenue

Merrill Avenue shifted south. New all-way stops on Merrill Avenue at Sultana Avenue and Bon View Avenue. Grove Avenue and Bon view Avenue are closed from Eucalyptus Avenue to Merrill Avenue.


Timeline:

Merrill Avenue is to be completed in 2024.


Construction Continues: The construction efforts are moving forward as planned, with the current focus being on the north side of Merrill Avenue. In the current phase, construction has shifted the roadway to the south side of Merrill. To ensure minimal disruption to traffic, a single lane in each direction will remain open on Merrill Avenue, spanning from Euclid Avenue to Archibald Avenue. Drive with caution and be aware of traffic control measures in the area.


Grove Ave Closure: Grove Avenue will remain closed (Eucalyptus Avenue to Merrill Avenue) for an extended duration. Please consider alternative routes via Sultana, Bon View Avenue and Carpenter Avenue.


All-Way Stops: Temporary all-way stops are at intersections on Merrill Avenue at Sultana Avenue, Bon View Avenue and Hellman Avenue. New traffic signals are in the works to enhance safety and traffic management.


Upcoming Closures: Short-term lane and roadway closures along Merrill Avenue are expected. No future long-term closures are planned.


Euclid Ave Enhancements: Euclid Avenue will also continue to experience construction activity, with public improvements continuing from Eucalyptus Avenue to Merrill Avenue, including significant modifications at the signalized intersections and frontage improvements.


More About the Project:

As part of the Ontario Ranch Business Park development, extensive improvements to Merrill Avenue near the intersection of Euclid are underway. The Ontario developer will be installing major underground utilities like sewer, storm drain and water connections.

Access to the Chino Airport and its businesses will be maintained at all times from the east on Merrill Avenue at Bon View Avenue.


Ramona Avenue Sewer Main Replacement

Impact: Yorba Avenue, Southbound Lane, from Edison Avenue to Schaefer Avenue

The southbound lane of Yorba Avenue will be narrowed to a single lane during work hours.


Timeline: November 27th to December 15th


More About the Project:

This is necessary to facilitate the installation of a new manhole and conduct essential sewer repairs.


Please pay attention to the NO PARKING signs that will be displayed before the commencement of work. These restrictions are critical for the safety and efficiency of the construction process. Flaggers will be on-site to guide traffic safely through the work zone. We urge all drivers to follow their directions and drive cautiously.


Access to all businesses along Yorba Avenue will remain open at all times. We are committed to minimizing disruptions to local businesses.


At the end of each workday, traffic flow on Yorba Avenue will be restored to its usual pattern.


PRESERVE ROAD IMPROVEMENTS



Bickmore Avenue from Euclid Avenue to Quality/Mayhew

Impact:

Bickmore Avenue is open in both directions. The developer continues to complete street improvements including the final cap paving of the street. Current efforts are focused on completing the improvements along the project frontage on Euclid Avenue. Euclid Avenue northbound is currently reduced to one lane during frontage improvement construction.



Timeline:

Early 2024.


More about the Project:

Work completed included sewer and storm drain improvements as a condition of the Alere development. Additional public improvements will be ongoing and may include temporary lane reductions.


Pine Avenue Storm Drain Installation "Line C"

Impact:

Lane closures between East Preserve Loop Avenue and Rincon Meadows Avenue. At least one lane to remain open in each direction at all times. West Preserve Loop will be closed from Moonspinner Street and Pine Avenue work in the intersection of Pine Avenue and West Preserve Loop.


Timeline:

September 2023- Winter 2024. Work will restart after the new year. New closure dates to be determined.


More About the Project:

As part of the development of the Town Center at The Preserve, Pine Avenue between West Preserve Loop and Harvest/Homecoming is being improved. Improvements include widening the road to 5 lanes, 2 new traffic signals, repaving of Pine and installation of underground utilities & center medians. Once completed, this project will relieve congestion & improve traffic flow on Pine Avenue.


Kimball Avenue from Euclid Avenue to Rincon Meadows


Impact:

Intermittent off-peak lane closures with at least one lane open at all times. To complete work on remedial items.


Timeline:

Completion of remedial items scheduled for end of Winter 2024. Work has been completed; punch-list items remain which may require occasional lane closures outside of peak hours.


More About the Project:

As part of the ongoing development in The Preserve, Kimball Avenue, between Euclid Avenue and Rincon Meadows Avenue is being improved to include the installation of underground utilities, raised median, streetlights, traffic signals and the installation of a large storm drain to help reduce flooding in the area.


Kimball Avenue Widening & Storm Drain Improvements

Project:

As part of ongoing development in The Preserve, the next phase of improvements for Kimball Avenue will soon be underway. This phase focuses on two key initiatives:


Installing a Reinforced Concrete Box to bridge the North and South Basins near Quality Way. Widening to full two lanes on north side of Kimball Ave from Rincon Meadows to Main Street.


Impact:

Single lane closure with occasional full closures overnight and on weekends. Specific dates to be determined.

Implementation of concrete K-Rail for grading operations behind traveled lanes.


Timeline:

Early spring 2024.


Project Schedule/Milestones:

Staging of K-Rail begins September 11. Stay tuned for more details on the project timeline, including the precise dates for lane closures. We are committed to keeping you informed every step of the way, and any full closures will be communicated in advance.


City Actions:

In our commitment to keeping you informed, we will take the following steps:

Notices: Residents south of Kimball Ave and businesses in the vicinity of the construction area will receive notifications with pertinent information. Regular updates will be provided via the construction newsletter and construction portal.

County Airport Coordination: We have coordinated with the San Bernardino County Airport regarding the construction activities.

Full Closures: Please note that full closures will only take place during overnight hours and on weekends to minimize disruption.

60/Central Avenue Interchange Improvements

SBCTA would like to extend our appreciation to the SR 60/Central Avenue Interchange Project community for your patience and partnership during construction. As the project enters its final weeks of construction, crews are finishing up striping and installing new landscaping and signage along the project corridor.

Learn More

Projects From Neighboring Communities

Eucalyptus Avenue - City of Ontario

Impact:

The City of Ontario has approved a road closure on Eucalyptus Avenue, stretching from Euclid Avenue to Sultana Avenue, beginning this week. This closure is necessary to facilitate the installation of underground utilities required for the REDA industrial project. While this closure is not directly located in Chino, it will have a significant impact on Chino commuters who use this route.



Timeline:

Road closure on Eucalyptus Avenue (from Euclid to Sultana) begins next week.

Closure is expected to last for approximately 5 months, impacting commuters during this period.

71/91 Interchange Project (RCTC)

Nightly Closures of E/B 91

SR-71 and SR-91 Lane Closures

Impact:

The Riverside County Transportation Commission’s 71/91 Interchange Project will require nightly full closures (Monday through Wednesday) of the westbound 91 between State Route 71 and Green River Road beginning Monday, December 11, 2023 through Wednesday, January 24, 2024.


Due to the holidays, no closures will be scheduled from December 20 through January 1, 2024. Closures will resume on Tuesday, January 2, 2024.


More About the Project:

The Riverside County Transportation Commission, in partnership with Caltrans, is reconstructing the 71/91 Interchange Project in Corona.


The new non-tolled interchange is designed to improve safety, expand access to other modes of travel, reduce greenhouse gas emissions, enhance traffic flow, and support continued movement of native wildlife through the area. Construction will take place from early 2023 to 2025.

Learn More

Crews paving over a newly installed drainage system on the SR 60/Central Avenue mainline.

Discover all you need to know about construction projects in our community at the City of Chino's Construction Portal. Get project details, timelines, and updates on capital improvements and developer-led projects.

Construction Portal
Facebook  Twitter  Instagram  Youtube  Linkedin