Benson Avenue and Portsmouth Street
Impact:
Please anticipate lane narrowing and occasional flagging as work proceeds with at least one lane in each direction always available.
Starting this week, the contractor will initiate mobilization and perform preliminary investigative work on the street section. Following this phase, the team will proceed to the trenchwork, progressing to repair the sewer line as needed.
Timeline:
The project is scheduled from June 1st through June 16th, 2023.
More About the Project:
The scope of this project includes establishing a new connection from a sewer lateral to the main sewer line on Benson Avenue.
Chino High School
Impact:
Lanes have shifted; one lane will be maintained in each direction at all times.
Timeline:
10th Street and Jefferson Avenue - Anticipated opening week beginning of June 2023.
Benson Avenue and 10th St - Street Paving will be finished June 2023.
Central Avenue, Dupont Avenue & D Street
Impact:
Intermittent lane closures with at least one lane open in each direction at all times. Streets Impacted:
- Dupont Avenue, Gates Street and Alton Street.
- Central from Chino to C Street
- D Street from Central to 5th Street
Timeline:
Final pavement restoration and roadway striping are still outstanding.
Dupont Avenue from April 6, 2023, through. summer 2023.
Central Avenue & D street from April 12, 2023, through summer 2023.
More About the Project:
Street improvements include pothole work and storm drain installation.
Central Avenue at Eucalyptus Avenue
Impact:
Temporary lane closures at the intersection.
Timeline:
Completion expected late spring 2023. Roadway striping are still outstanding.
More About the Project:
Public improvements to roadway, sidewalk and traffic signal. Final pavement restoration and roadway striping are still outstanding.
Chino Avenue between Mountain Ave and Bunker Hill Place
Impact:
Intermittent lane closures with at least one lane open in each direction at all times.
Timeline:
From June 1st to June 9th, 2023, asphalt and concrete in five lanes will be removed and replaced with new crosswalk concrete, involving closure and reopening of lanes in stages to minimize disruption.
Completion expected summer 2023. SCE and utility companies need to relocate their conflicting utilities.
More About the Project:
Street improvements include pothole work and storm drain installation. Completion date projection extended due to relocation of utilities.
D Street from Monte Vista Avenue to 2nd Street
Impact:
Intermittent lane closures.
Timeline:
Monday, January 30 through June 2023.
Detour Information:
2nd Street to C Street or Chino Avenue.
More About the Project:
Public improvements include storm drain, curb, gutter, sidewalk, pedestrian ramps and crosswalks. Local access will be maintained.
Edison Avenue from Central Avenue to east of Oaks Avenue
Impact:
Driveway at YMCA building is closed.
Timeline:
End of summer 2023.
Detour Information:
Access YMCA via 12th entrance on Edison Avenue or from College Park Avenue.
More About the Project:
Construction of storm drain, street widening, curb, gutter & sidewalk, pavement rehabilitation, Ayala Park entrance improvements, traffic signal improvements, and pedestrian accessibility improvements as part of the College Park ultimate Improvement Project.
Merrill Avenue from Euclid Avenue to Stearman Drive
Impact:
Full 24-hour closure in both directions. Bon View Avenue closed from Eucalyptus Avenue to Merrill Avenue.
Timeline:
Begins Friday, February 10, 2023, through early June 2023. (Recent rain events have impacted the end date.)
Detour Information:
Grove Avenue from Eucalyptus Avenue and Merrill Avenue
More About the Project:
As part of the Ontario Ranch Business Park development, extensive improvements to Merrill Avenue near the intersection of Euclid are underway. The Ontario developer will be installing major underground utilities like sewer, storm drain and water connections.
Access to the Chino Airport and its businesses will be maintained at all times from the east on Merrill Avenue at Bon View Avenue.
Ramona Avenue (Chino Hills Parkway City to Philadelphia Avenue)
Impact:
One lane closure Prep work (Striping removals, crack seal, and patch repair)
Timeline: May 30-June 9
More about the Project:
Slurry seal June 12-June 21, Striping - July 5-July 7.
Olive Place at Walnut Avenue
Impact:
Intermittent lane closures with at least one lane open in each direction at all times.
Timeline:
Completion expected end of May 2023.
More About the Project:
Street Improvements to include sidewalk, curb and gutter, and pedestrian accessibility improvements.
|