Paving - the most disruptive portion of this phase - is scheduled for the last week of July and the first week of August, specifically July 25 & 26 and July 31 - August 2. This is the only portion of the project where residential access may be restricted.
We will follow up with email blasts to the whole community and village-specific communications as we approach the work that most impacts our residents. We plan to do everything possible to minimize resident disruption to the extent possible.
We expect the bulk of construction to be complete by the first week of August, with striping and final utility adjustments completed the week of August 12.
In the meantime, please be cautious while driving. The various vendors are on property throughout the month of July and into August, preparing for and executing the project.
Best Regards,
Alex Wright
Interim Community Manager
|