Construction Update
U.S. Route 7, Charlotte-South Burlington
DATE: Thursday, 8/4/22

TRAFFIC IMPACT:

Motorists can expect lane closures in the vicinity of active construction operations along Route 7 in Charlotte throughout the week of 8/7 during nighttime work hours. Traffic control personnel will be onsite helping to direct the flow of traffic. Please expect delays.

CONSTRUCTION ACTIVITIES:

Milling operations will continue throughout the week of 8/7/22, progressing from south to north. It is anticipated that the contractor will be in Shelburne Village late in the week next week.

There is a possibility that paving of the leveling course (not the final layer) of asphalt will begin late next week beginning on the south end near Charlotte Crossings and progress to the north. Expect crews to be on the roadway at approximately 7:00 p.m.

Work on this contract will be performed at night. Typical nighttime work hours are 7:00 p.m.-6:00 a.m. Sunday through Thursday night. It should be noted, however, that work may be performed at times on Friday nights.

Residents and business owners should anticipate increased noise levels during construction activities. The construction area will also have increased lighting overnight in order to ensure the safety of the crew. The contractor will take necessary measures to ensure noise levels remain within approved decibel levels.

Viewing from a website/social media platform? Click below to receive updates
directly to your inbox.
Milling operations have begun at the southern project limit in Charlotte and will continue progressing to the north throughout the remainder of this week and next week.

LOCATION: This project begins on U.S. Route 7 in Charlotte from the vicinity of Brown Lane (south of Ferry Road) and continues northerly for 10.2 miles to the intersection with Swift Street in South Burlington.
The project area during the 2022 construction season includes U.S. Route 7 from Charlotte to Webster Road (the jug handle) in Shelburne.

PROJECTED COMPLETION: Fall 2023
Contact Information:
Name - Natalie Boyle
Phone - 802-855-3893
Email - nboyle@eivtech.com
To learn more about VTrans Construction Projects, visit our projects website.