Thursday, July 9, 2026

SH-16, I-84 to SH-44 | Progress Tracker

The new SH-16 corridor is expected to open in mid-2027.

60% complete: ____________________

Read below to learn about progress along the corridor!

Click the photo to learn more!

I-84 System Interchange

⬣ Over the past month, crews have made progress on the bridge decks (top of bridge) of each flyover ramp crossing I-84. Crews have also started repaving I-84 between Ten Mile (Exit 42) and Garrity (Exit 38).

► Upcoming: Full closures on eastbound and westbound I-84 will take place later this month as crews restripe I-84 and place concrete for the bridge deck. ITD is also repaving ramps along I-84 starting next week. Click for more information.

Click the photo to learn more!

Franklin Interchange

⬣ Since our last update, crews have added pavement markings to the top of the interchange bridge and finished paving the on- and off-ramps.

Click the photo to learn more!

Ustick Interchange

⬣ In the last month, crews have begun work to install lighting under the interchange bridge. Crews are also installing the median barrier on top of the interchange bridge.

Click the photo to learn more!

US-20/26 Interchange (Chinden Blvd)

⬣ Since our last update, crews finished paving the loop ramp and began placing curb and gutter around the interchange.

Click the photo to learn more!

SH-44 Interchange (State St)

⬣ Over the past month, crews have paved and connected the future northbound on and off ramps to the roadway.

► Upcoming: Crews will continue paving work in the center of SH-44 and around the intersection. A traffic shift will also take place next month, more information to come.

*Estimated completion dates and schedules are subject to change.