April Update

The SH-55, Farmway to Middleton project is wrapping up the third month of construction. Read below to learn about work that happened in the month of March and what's planned for April.

What happened in March:

  • Continued preparing SH-55 for widening
  • Graded and excavated earth around the roadway
  • Continued work on irrigation and water utilities under and around the roadway

What's planned for April:

  • Grading on the sides SH-55 to prepare for widening
  • Preparing for construction of Karcher View Street
  • Continuing work on irrigation and water utilities under the roadway
  • Excavating embankment between Lake and Midway

We are taking every possible measure to reduce delays and other traffic impacts, and there are no road or lane closures planned for the month of April. However, the project schedule may change. To get the latest information on closures, sign up to receive text alerts by clicking here or the button below.

Sign up for Text Updates
Sign up for Email Updates
Download project fact sheet
Download this bulletin

Se les recomienda a las personas que necesiten un intérprete o arreglos especiales que llamen al 208-334-8496. Usuarios de TTY/TDD: Marque 711 o (800) 377-3529 para usar el sistema de Relay de Idaho.


Persons needing an interpreter or special accommodations are urged to contact 208-334-8884 or TTY/TDD users Dial 711 to use the Idaho Relay System.