Public Lands posted a request for qualification for consultants to submit for the Allen Park Adaptive Reuse and Management Plan.
The period for submission has closed and a City committee is now reviewing proposals for selection. We are hoping to have a consultant selected, under contract and beginning public engagement by the end of October 2022.
Additionally, we are finishing up detailed design for three utility lines to be placed under Allen Park Drive: fire suppression line, irrigation line and a water/sewer line. We are hoping to finish design by the end of October and begin construction in the spring.
We have also received a structural report for the main Allen Lodge and are working towards a roof replacement that will ensure the Lodge remains watertight throughout the winter season.
Allen Park is located at 1328 Allen Park Drive.