Phase 1 is currently under construction and anticipates final completion in fall 2024. Phase 1 includes a 30- acre marshaling space, referred to as Parcel A containing a heavy-lift wharf and uplands that will facilitate the offloading, testing, inspection, and pre-assembling of wind turbine generation components before their installation offshore, commonly referred to as Offshore Wind (OSW) Marshaling; and the main electrical substation, which will provide power to Parcel A and all other future parcels planned in the property’s total development.
The wharf in Parcel A is 1,080 linear feet and comprises delivery and installation berths to support load-in and load-out operations. Further, the pile-supported pier has a load-bearing capacity of 6,200 pounds per square foot at the concrete deck surface.
The port has also been future-proofed with the inclusion of a breasting dolphin and two mooring dolphins to accommodate a US flagged wind turbine installation vessel.
To date, all dredging associated with Phase 1 has been completed in coordination with NJEDA partners, the NJDOT Office of Maritime Resources and AECOM-Tishman. The access channel and berth areas are dredged to -35.5 feet, with an installation berth pocket of -47.5 feet.
Another critical part of Phase 1 is the completion of the wind port’s main electrical substation. The switchgear building, transformers, and fencing/yard area have been installed with testing and commissioning of components on-going. Substantial completion of the substation is anticipated by early November 2024.
To receive power, Atlantic City Electric (ACE) is constructing approximately 13 miles of new transmission line from an existing substation in Quinton Township to conduct power to the port. ACE is anticipated to be substantially completed with the installation of the transmission line testing of the electrical connections to the substation and conduct testing of the electrical connections to the substation by the end of Fall 2024.
| | |
|
FIGURE 1: Parcel A uplands have received subbase and base course layers of aggregate that reflect the finished product (see fig. 1). Upon completion, the uplands area is rated for 3,000 psf long-term and 4,800 psf short-term (~1 year) static loading of wind turbine generation components. | | |
FIGURE 2: The current construction status of the main substation as of September 2024. This work will include the substation and the duct bank that houses the conduit for transmission power from the substation to the various wind port parcels. | |
| |
Parcel B1 commenced construction for Stage 1 earthwork operations in January 2024 and has completed initial filling operations, wick drain installation, geotechnical monitoring instrumentation installation, mechanically stabilized earth (MSE) wall construction, and surcharge embankment construction.
Surcharge embankment construction was completed in September 2024 and geotechnical instrumentation monitoring is actively on-going and will extend during the duration of the embankment hold period estimated to be approximately 6 months from the date of final embankment construction.
The Parcel B1 earthwork project is approximately 95% complete. A test pile program consisting of 44 precast concrete piles was completed in April 2024 to inform the wharf design for B1.
Parcel C1 surcharge embankment was fully removed in early May 2024 and the area prepared for future sitework construction operations.
Parcel G Advanced Sitework is approximately 90% complete. Construction consists of roadway modifications, temporary stormwater drainage, electric duct bank construction, and associated site feature infrastructure.
Phase 2 permitting is progressing broadly on schedule, as is design. Development is slated to begin in 2025.
| | |
Diversity Participation Goals
| |
Goal Expectation | Commitment | Percentage Achieved | MWVBE Goal 15% | $140,155,797.94 | 47.39% | SBE Goal 3% | $78,019,907.40 | 26.38% | SDVOB Goal 3% | $9,211,191.40 | 3.11% | Local Business | $163,872,131.12 | 55.41% | | |
|
NJ Wind Port Profile:
NJWP's Project Manager provides an in-depth look at the extensive infrastructure efforts powering the New Jersey Wind Port. By spearheading the development of this crucial hub, he underscores how it will serve as a key driver in scaling offshore wind projects throughout the East Coast.
| | |
Atlantic Shores Project's 1 and 2 Construction and Operations Plans Approved
Atlantic Shores Offshore Wind has received Construction and Operations Plan (COP) approvals from the Bureau of Ocean Energy Management (BOEM) for Atlantic Shores Projects 1 and 2, which combined will generate enough renewable energy to serve more than 1 million New Jersey homes.
Atlantic Shores Project 1 is New Jersey’s first offshore wind project and COP approval will enable the near-term creation of thousands of in-demand jobs and acceleration of billions of dollars in supply chain investments being made in the Garden State. Atlantic Shores Project 2 will build on this first-mover success and drive economic growth across the state over the next decade.
| | |
NJEDA Receives Notice of $50M Award for Federal Grant to Advance Offshore Wind Development in NJ
The New Jersey Economic Development Authority (NJEDA) received a notice of a $50 million funding award through the United States Department of Energy’s (USDOE) Transmission Siting and Economic Development (TSED) Grant Program.
Upon NJEDA Board approval of the grant award, the NJEDA and its collaborators plan to fund a portfolio of initiatives that will prepare local residents for careers in the clean energy industry. It will also fund local projects designed to increase civic engagement, and further economic mobility in communities with new renewable transmission infrastructure.
| | |
Time for Turbines 7 presented by Jersey Renews
Thursday, October 10th &
Friday, October 11th
Atlantic City, NJ
This full 2-day conference will feature an opening session, a networking lunch, and field trips to offshore wind and marine science sites.
| | |
New Jersey and New York
Offshore Wind Supplier Forum
Monday, October 28th
Atlantic City, NJ
This event will convene the regional offshore wind industry with local businesses looking to supply its products and services to projects on the East Coast.
| | |
ACP Offshore WINDPOWER Conference & Exhibition
Monday, October 28th - Wednesday, October 30, 2024
Atlantic City, NJ
This event will convene top developers, government officials, and key stakeholders across the industry who are working to achieve the full promise of U.S. offshore wind. Join over 2,400 attendees, including decision-makers with purchasing power, and engage with 75+ top speakers across three stages.
| | |
NJEDA Launches NJ Wind Port Website
& Offshore Wind Hub
| |
New Jersey Offshore Wind Hub | |
|
Green Workforce Training Grant Challenge
The Green Workforce Training Grant Challenge is a competitive funding opportunity that will award grants to implement workforce development training programs that bolster the green economy talent pipeline in the state with a particular focus on NJ’s Overburdened Communities.
A total of $7 million is available for programs under this Grant Challenge, including $2.65 million from the Wind Institute for Innovation and Training and $4.35 million through the Governor’s Council on the Green Economy.
Applications are being accepted through 5:00 p.m. on Tuesday, October 8th.
| | |
|
RFI for Apprenticeship Training Centers and Construction Grants
The New Jersey Economic Development Authority (NJEDA) has issued a Request for Information (RFI) seeking insight from qualified entities that provide registered apprenticeship programs and have perspectives on establishing new registered apprenticeship training locations in Overburdened Communities. The information gathered through the RFI will determine the scope and characteristics of a grant program to support the planning and implementation of new/expanded training facilities.
All RFI responses must be submitted in writing no later than 5:00 p.m. on Tuesday, October 15th.
| | | | | |