PAVING SCHEDULE
WHEN: Wednesday 7/ 24 (Weather Permitting)
Milling Begins:
S.L. Williamson Company Inc. will edge mill the entire length of the roadway to maintain the original elevation after paving. Milling will proceed in the following order: pink, yellow, blue, red, and green designated areas. This approach is expected to minimize disruption for residents..
Paving Begins:
Monday 7/29 – Pink area
Devon Pines, Newbridge Road, Downing Court & Westerham Street
Tuesday 7/30 – Yellow area
Farringdon Road & Charterhouse Court
Wednesday 7/31 – Blue area
Wallingford Lane, Avebury Lane & Perth Court
Thursday 8/1 – Red area, possibly get into the Green area
Kingsbridge Trail, Elgin Court & Dane Court
Friday 8/2 – wrap up paving
Prestwick Place & Kinross Lane
Pavement Markings: Will be completed the week of August 5th.
Parking: Park in your driveway or garage. Avoid parking on the street during this time.
IMPORTANT PAVING INFORMATION
Before paving starts
- Park in your garage or driveway – do not park on the street.
- Move your vehicle(s) off the street and park on your lot.
During paving
- One lane of roadway should be available at all times for travel.
- Please follow the direction of the paving crew personnel when traveling in the community.
After paving
- You will be able to drive on the asphalt as soon as it has been rolled a few times.
-
If the street is paved when you return home, parking on the paved streets is allowed.
We appreciate your patience and support
|