2nd UPDATE!

Phase 3 of GCA's Road Paving Project

July 26, 2024

We sincerely apologize for multiple bulletins and date changes to this project. However, due to weather & breakdowns outside the contractor’s control, the dates for Milling and Paving have once again changed. 


Please take note of the date changes below.

Attention Residents of:

Devon Pines, Newbridge Road, Downing Court, Westerham Street;

Farringdon Road & Charterhouse Court; Avebury Lane, Perth Court, Wallingford Lane; Kingsbridge Trail, Elgin Court & Dane Court;

Prestwick Place & Kinross Lane

Dear Nancy,

S.L. Williamson Company Inc. will now begin prep work:


Milling to begin

Monday, 7/29/24 - Wednesday, 7/31/24


Milling Schedule:

S.L. Williamson Company Inc. will edge mill the entire length of the roadway to maintain the original elevation after paving. Milling will proceed in the following order: pink, yellow, blue, red, and green designated areas. This approach is expected to minimize disruption for residents.


Please inform your service providers to avoid accessing your street on the specified dates. If necessary, ask them to park on adjacent streets and remind them not to park on the grass.


Flaggers will be on site to assist residents with navigating in and out of the roadways. While operations may cause some delays, these will be brief, and no one will be blocked for an extended period.

PAVING SCHEDULE


Paving Begins:

Thursday 8/01 – Pink area

Devon Pines, Newbridge Road, Downing Court & Westerham Street

Friday 8/02 – Yellow area

Farringdon Road & Charterhouse Court

Monday 8/05 – Blue area

Wallingford Lane, Avebury Lane & Perth Court

Tuesday 8/06 – Red area, possibly get into the Green area

Kingsbridge Trail, Elgin Court & Dane Court

Wednesday 8/07 – wrap up paving

Prestwick Place & Kinross Lane


Pavement Markings: Tentatively August 7th & 8th and the week of August 12th


Parking: Park in your driveway or garage. Avoid parking on the street during this time.

 

IMPORTANT PAVING INFORMATION


Before paving starts

  • Park in your garage or driveway – do not park on the street.
  • Move your vehicle(s) off the street and park on your lot.

During paving

  • One lane of roadway should be available at all times for travel.
  • Please follow the direction of the paving crew personnel when traveling in the community. 

After paving

  • You will be able to drive on the asphalt as soon as it has been rolled a few times.
  • If the street is paved when you return home, parking on the paved streets is allowed.


We appreciate your patience and support.