PAVING SCHEDULE
Paving Begins:
Thursday 8/01 – Pink area
Devon Pines, Newbridge Road, Downing Court & Westerham Street
Friday 8/02 – Yellow area
Farringdon Road & Charterhouse Court
Monday 8/05 – Blue area
Wallingford Lane, Avebury Lane & Perth Court
Tuesday 8/06 – Red area, possibly get into the Green area
Kingsbridge Trail, Elgin Court & Dane Court
Wednesday 8/07 – wrap up paving
Prestwick Place & Kinross Lane
Pavement Markings: Tentatively August 7th & 8th and the week of August 12th
Parking: Park in your driveway or garage. Avoid parking on the street during this time.
IMPORTANT PAVING INFORMATION
Before paving starts
- Park in your garage or driveway – do not park on the street.
- Move your vehicle(s) off the street and park on your lot.
During paving
- One lane of roadway should be available at all times for travel.
- Please follow the direction of the paving crew personnel when traveling in the community.
After paving
- You will be able to drive on the asphalt as soon as it has been rolled a few times.
-
If the street is paved when you return home, parking on the paved streets is allowed.
We appreciate your patience and support.
|