CONSTRUCTION ACTIVITIES -
Week of April 5, 2021
BRIDGE WORK
The week of April 5, crews will continue work on the retaining walls along the EB SR 210 Base Line on-ramp, perform concrete pours on SR 210 at 5th Street, and continue constructing temporary bridge supports, also known as falsework, at Highland Avenue and Arden Avenue. The following nighttime closures of EB and WB SR 210 are needed to facilitate this work:

  • EB SR 210 Closed between 5th Street and San Bernardino Avenue - Closed from 10:00 p.m. Thursday, April 8 to 5:00 a.m. Friday, April 9. DETOUR: Exit EB SR 210 at 5th Street and turn right at the end of the ramp, turn left on Alabama Street, then turn left on San Bernardino Avenue to reenter EB SR 210 via the on-ramp.

  • WB SR 210 Closed between San Bernardino Avenue and 5th Street - Closed overnight from 10:00 p.m. to 5:00 a.m., Monday, April 5 and Tuesday, April 6 (into Wednesday morning). DETOUR: Exit WB SR 210 at San Bernardino Avenue and turn right at the end of the ramp, turn right on Alabama Street, then turn right on 5th Street to reenter WB SR 210 via the on-ramp.

Bridge widening activities are underway during daytime and nighttime shifts, at numerous locations throughout the project area, including 5th Street, Pioneer Avenue, Victoria Avenue, Base Line Interchange, and Highland Avenue. Visit the Google map above (project Google map) for the most up-to-date closures scheduled and available detour routes.
Pictured below, crews continue place concrete for the widening of the SR 210 at Access Road.
SR 210 LANE, CONNECTOR, AND RAMP CLOSURES
Connector Closures:
  • EB I-10 Connector to WB SR 210 -
  • Overnight from 9:00 p.m. to 5:00 a.m., Monday, April 5 and Tuesday, April 6 (into Wednesday morning).

  • EB SR 210 Connector to EB I-10 -
  • Closed from 9:00 p.m. Tuesday, April 6 to 5:00 a.m. Wednesday, April 7.

Ramp Closures:

  • EB/WB SR 210 On-Ramps and Off-Ramps at Base Line - 
  • Nightly from 8:00 p.m. to 6:00 a.m., Monday, April 5 through Thursday, April 8 (into Friday morning).
  • Overnight from 9:00 p.m. to 7:00 a.m., Friday, April 9 and Saturday, April 10 (into Sunday morning).

  • WB SR 210 On-Ramp at San Bernardino Avenue - 
  • Overnight from 8:00 p.m. to 6:00 a.m., Monday, April 5 and Tuesday, April 6 (into Wednesday morning).

  • EB SR 210 On-Ramp at 5th Street -
  • From from 8:00 p.m. Thursday, April 8 to 6:00 a.m. Friday, April 9.

Please note, nighttime lane/ramp closures may occur intermittently along EB and WB SR 210, between Del Rosa Avenue and I-10, Mondays through Saturdays (into Sunday mornings), from 8:00 p.m. to 6:00 a.m. No two consecutive ramps will be closed at the same time. In addition, crews will continue daytime and nighttime construction activity along SR 210 as well as on local city streets.
LOCAL STREET CLOSURES
Highland Avenue at SR 210 - Full closure between the EB SR 210 off-ramp and Arden Avenue, nightly from 9:00 p.m. to 6:00 a.m., Monday, April 5 through Wednesday, April 7 (into Thursday morning) and from 9:00 p.m. to 11:59 p.m. on Thursday, April 8.






Arden Avenue at SR 210 -
Full closure at SR 210 nightly from 9:00 p.m. to 6:00 a.m., Monday, April 5 through Wednesday, April 7 (into Thursday morning) and from 9:00 p.m. to 11:59 p.m. on Thursday, April 8.
5th Street at SR 210 -
Closed nightly from 9:00 p.m. to 6:00 a.m., Monday, April 5 through Friday, April 9 (into Saturday morning).
Victoria Avenue at SR 210 - Closed nightly from 9:00 p.m. to 6:00 a.m., Monday, April 5 through Friday, April 9 (into Saturday morning).
ABOUT THE PROJECT
The SR 210 Lane Addition and Base Line Interchange Project is designed to provide increased traffic flow throughout this corridor. To eliminate the existing bottleneck and provide lane continuity, the SR 210 will be widened from Sterling Avenue to San Bernardino Avenue in the cities of San Bernardino, Highland, and Redlands, as well as an unincorporated portion of San Bernardino County. Base Line Interchange will also be widened from Buckeye Street to Seine Avenue in the City of Highland, which will include widening three of the four interchange ramps. As the SR 210 Lane Addition and Base Line Interchange projects aligned geographically and shared similar delivery schedules, they were combined for the design, right-of-way, and construction phases to save cost and expedite the schedule. In addition, pavement rehabilitation work was added through a cooperative agreement with Caltrans that includes new concrete pavement between 5th Street and Lugonia Avenue. Adding the pavement rehabilitation work during the Lane Addition and Base Line Interchange projects means one less project that the community will have to navigate around in the future.

Please remember construction is dynamic and the schedule is subject to change.