CONSTRUCTION ACTIVITIES -
Week of February 8, 2021
In observance of Presidents Day, there will be no closures scheduled Friday, February 12 through Monday, February, 15.
BRIDGE WORK
The week of February 8, crews will continue work on the retaining wall along the EB SR 210 Base Line on-ramp and will perform work on the retaining wall along the WB SR 210 on-ramp at Base Line, and perform concrete pours on SR 210 at Santa Ana River . The following nighttime closures of EB and WB SR 210 are needed to facilitate this work:

  • EB SR 210 Closed from 5th Street to San Bernardino Avenue: Closed overnight from 10:00 p.m. to 5:00 a.m., Monday, February 8 and Thursday, February 11 (into Friday morning). DETOUR: Exit EB SR 210 at 5th Street and turn right at the end of the ramp, turn left on Alabama Street, then turn left on San Bernardino Avenue to reenter EB SR 210.

  • WB SR 210 Closed from San Bernardino Avenue to 5th Street: Closed overnight from 10:00 p.m. to 5:00 a.m., Monday, February 8 and Wednesday, February 10 (into Thursday morning). DETOUR: Exit WB SR 210 at San Bernardino Avenue and turn right at the end of the ramp, turn right on Alabama Street, then right on 5th Street to reenter WB SR 210.

Bridge widening activities are underway during daytime and nighttime shifts, at numerous locations throughout the project area, including 5th Street, Pioneer Avenue, Victoria Avenue, Base Line Interchange, and Highland Avenue. Visit the Google map above (project Google map) for the most up-to-date closures scheduled and available detour routes.
Pictured here, crews are removing temporary bridge supports also known as falsework from the 5th Street bridge at SR 210.
SR 210 LANE, CONNECTOR, AND RAMP CLOSURES
Connector Closures:
  • EB I-10 Connector to WB SR 210 -
  • Overnight from 8:00 p.m. to 6:00 a.m., Monday, February 8 and Wednesday, February 10 (into Thursday morning).

Ramp Closures:

  • EB SR 210 On-Ramp at Base Line -
  • Overnight from 8:00 p.m. to 6:00 a.m., Tuesday, February 9 and Wednesday, February 10 (into Thursday morning).

  • EB SR 210 Off-Ramp at Base Line -
  • Nightly from 8:00 p.m. to 6:00 a.m., Monday, February 8 through Thursday, February 11 (into Friday morning).

  • WB SR 210 On-Ramp at Base Line -
  • Nightly from 8:00 p.m. to 6:00 a.m., Monday, February 8 through Thursday, February 11 (into Friday morning).

  • WB SR 210 Off-Ramp at Base Line -
  • Overnight from 8:00 p.m. to 6:00 a.m., Wednesday, February 10 through Thursday, February 11 (into Friday morning).

  • WB SR 210 On-Ramp at 5th Street -
  • Overnight from 8:00 p.m. to 6:00 a.m., Monday, February 8 and Wednesday, February 10 (into Thursday morning).

  • WB SR 210 Off-Ramp at 5th Street -
  • Overnight from 8:00 p.m. to 6:00 a.m., Monday, February 8 and Tuesday, February 9 (into Wednesday morning).

  • EB SR 210 On-Ramp at 5th Street -
  • Overnight from 8:00 p.m. to 6:00 a.m., Monday, February 8 and Thursday, February 11 (into Friday morning).

  • WB SR 210 On-Ramp at San Bernardino Avenue -
  • Overnight from 8:00 p.m. to 6:00 a.m., Monday, February 8 and Wednesday, February 10 (into Thursday morning).

Please note, nighttime lane/ramp closures may occur intermittently along EB and WB SR 210, between Del Rosa Avenue and I-10, Mondays through Fridays (into Saturday mornings), from 8:00 p.m. to 6:00 a.m. No two consecutive ramps will be closed at the same time. In addition, crews will continue daytime and nighttime construction activity along SR 210 as well as on local city streets.
LOCAL STREET CLOSURES
Highland Avenue at SR 210 - Full closure between the EB SR 210 off-ramp and Arden Avenue, nightly from 9:00 p.m. to 6:00 a.m., Monday, February 8 through Wednesday, February 10 (into Thursday morning) and from 9:00 p.m. to 11:59 p.m. on Thursday, February 11.


Arden Avenue at SR 210 - Lanes will be closed on Arden Avenue at SR 210, nightly from 9:00 p.m. to 6:00 a.m., Monday, February 8 through Wednesday, February 10 (into Thursday morning) and from 9:00 p.m. to 11:59 p.m. on Thursday, February 11. At least one lane in each direction will remain open on Arden Avenue at SR 210 at all times.
5th Street at SR 210 - Full closure underneath SR 210, overnight from 9:00 p.m. to 6:00 a.m., Monday, February 8 and Tuesday, February 9 (into Wednesday morning).



ABOUT THE PROJECT
The SR 210 Lane Addition and Base Line Interchange Project is designed to provide increased traffic flow throughout this corridor. To eliminate the existing bottleneck and provide lane continuity, the SR 210 will be widened from Sterling Avenue to San Bernardino Avenue in the cities of San Bernardino, Highland, and Redlands, as well as an unincorporated portion of San Bernardino County. Base Line Interchange will also be widened from Buckeye Street to Seine Avenue in the City of Highland, which will include widening three of the four interchange ramps. As the SR 210 Lane Addition and Base Line Interchange projects aligned geographically and shared similar delivery schedules, they were combined for the design, right-of-way, and construction phases to save cost and expedite the schedule. In addition, pavement rehabilitation work was added through a cooperative agreement with Caltrans that includes new concrete pavement between 5th Street and Lugonia Avenue. Adding the pavement rehabilitation work during the Lane Addition and Base Line Interchange projects means one less project that the community will have to navigate around in the future.

Please remember all construction is dynamic and the schedule is weather-permitting and subject to change.

Sign up for text messages by texting SR210Baseline to 31996 (Reply STOP to cancel, text HELP for help. Normal text and data message rates apply.

Si prefiere recibir información de construcción en español, llame al 877-55-SBCTA.