WESTBOUND SR 210 - 55 HOUR DIRECTIONAL FREEWAY CLOSURE

Friday, April 14 at 10:00 p.m. to Monday, April 17 at 5:00 a.m.

The first of six directional 55-hour freeway closures on SR 210 are now scheduled to begin on Friday, April 14 at 10:00 p.m. to Monday, April 17 at 5:00 a.m.

WB SR 210 will be closed from the I-10 connectors to 5th Street/Greenspot Road.


Drivers will not have access to the following:

  • Westbound (WB) SR 210 from the I-10 connectors to 5th Street/Greenspot Road
  • Eastbound (EB) I-10 connector to WB SR 210
  • WB I-10 connector to WB SR 210
  • EB San Bernardino Avenue on- and off-ramps


Detour:

  • From EB/WB I-10, exit Alabama Street and continue north. Turn right onto 5th Street/Greenspot Road to access the WB SR 210 on-ramp.


DIRECTIONAL, 55-HOUR FREEWAY CLOSURES

A series of six directional, 55-hour freeway closures on SR 210 as part of the SR 210 Lane Addition and Base Line Interchange Project are now scheduled to start on Friday, April 14. These closures will be taken one direction at a time over select weekends. The closures will allow crews to safely perform paving operations on EB and WB SR 210 at the on- and off-ramp junctures of the San Bernardino Avenue interchange. 


The directional closures will take place during weekends from Friday at 10:00 p.m. to Monday at 5:00 a.m. and are expected to be scheduled for the following dates*: 


  • Friday, April 14 through Monday, April 17 (WB)
  • Friday, April 21 through Monday, April 24 (WB)
  • Friday, April 28 through Monday, May 1 (WB)
  • Friday, May 5 through Monday, May 8 (EB)
  • Friday, May 12 through Monday, May 15 (EB)
  • Friday, May 19 through Monday, May 22 (EB)


* Please remember construction is dynamic and the schedule is subject to change.


For additional information about the closures, please visit goSBCTA.com/SR210BaseLine.

CONSTRUCTION ACTIVITIES - Week of April 10, 2023

FULL-FREEWAY CLOSURES

In addition to regularly scheduled nightly closures, WB SR 210 will be closed for 55-hours from Friday, April 14 at 10:00 p.m. to Monday, April 17 at 5:00 a.m. 


Crews will continue work on the retaining walls and sound walls along the SR 210 throughout the project area, as well as concrete paving activity. Crews are also finishing up remaining concrete ramps and sidewalk activity at Base Line. The following nighttime closures of EB and WB SR 210 are required to facilitate this work:

WB SR 210 Closed at Base Line - Closed overnight from 11:59 p.m. to 5:00 a.m., Monday, April 10 and Tuesday, April 11 (into Wednesday morning).


Only one WB freeway closure will be taken at a time.

EB SR 210 Closed at Base Line - Closed nightly from 11:59 p.m. to 5:00 a.m., Monday, April 10 through Wednesday, April 12 (into Thursday morning).


Only one EB freeway closure will be taken at a time.


WB SR 210 Closed at Highland Avenue - Closed from 11:59 p.m., Wednesday, April 12 to 5:00 a.m., Thursday, April 13.


Only one WB freeway closure will be taken at a time.


EB SR 210 Closed at Highland Avenue - Closed from 11:59 p.m., Thursday, April 13 to 5:00 a.m., Friday, April 14.


Only one EB freeway closure will be taken at a time.

Bridge widening activities are underway during daytime and nighttime shifts, at numerous locations throughout the project area, including 5th Street, Pioneer Avenue, Victoria Avenue, Base Line Interchange, and Highland Avenue. Visit the Google map above (project Google map) for the most up-to-date closures scheduled and available detour routes.

SR 210 LANE, CONNECTOR, AND RAMP CLOSURES

Connector Closures*:

The following connectors will be closed nightly from 9:00 p.m. to 5:00 a.m., Monday, April 10 through Thursday, April 13 (into Friday morning).


  • EB SR 210 Connector to WB I-10


  • EB SR 210 Connector to EB I-10


  • WB I-10 Connector to WB SR 210


  • EB I-10 Connector to WB SR 210


  • SB SR 330 Connector to EB SR 210


*In addition to regularly scheduled nightly closures, the EB and WB I-10 connectors to WB SR 210 will be closed for 55-hours from Friday, April 14 at 10:00 p.m. to Monday, April 17 at 5:00 a.m. during the WB SR 210 55-hour directional freeway closure.


Please visit the project Google map for detours for the above connector closures.

Ramp Closures*:

The following ramps will be closed nightly from 9:00 p.m. to 5:00 a.m., Monday, April 10 through Thursday, April 13 (into Friday morning). Please note, no two consecutive ramps will be closed simultaneously:


  • EB SR 210 Off-Ramp at Highland Avenue


  • EB SR 210 On-Ramp at Arden Avenue


  • WB SR 210 On-Ramp at Highland Avenue


  • EB SR 210 On-Ramp at Del Rosa Avenue


  • WB SR 210 Off-Ramp at Del Rosa Avenue


  • EB/WB SR 210 On- and Off-Ramps at Base Line


  • EB/WB SR 210 On-Ramps and WB Off-Ramp at 5th Street/Greenspot Road


  • EB/WB SR 210 On- and Off-Ramps at San Bernardino Avenue


*In addition to regularly scheduled nightly closures, the WB SR 210 on- and off-ramps at San Bernardino Avenue will be closed for 55-hours from Friday, April 14 at 10:00 p.m. to Monday, April 17 at 5:00 a.m. during the WB SR 210 55-hour directional freeway closure.


Please note, nighttime lane/ramp closures may occur intermittently along EB and WB SR 210, between Del Rosa Avenue and I-10, Mondays through Saturdays (into Sunday mornings), from 8:00 p.m. to 6:00 a.m. No two consecutive ramps will be closed at the same time. In addition, crews will continue daytime and nighttime construction activity along SR 210 as well as on local city streets.

LOCAL STREET CLOSURES

Highland Avenue at SR 210 - Closed nightly from 9:00 p.m. to 6:00 a.m., Monday, April 10 through Thursday, April 13 (into Friday morning).


Please note, Highland Avenue and Arden Avenue will not be closed simultaneously.

Arden Avenue at SR 210 - Closed nightly from 9:00 p.m. to 6:00 a.m., Monday, April 10 through Thursday, April 13 (into Friday morning).


Please note, Highland Avenue and Arden Avenue will not be closed simultaneously.

Base Line Street Closure at SR 210 - Closed nightly from 9:00 p.m. to 6:00 a.m., Monday, April 10 through Thursday, April 13 (into Friday morning).

Sterling Avenue at SR 210 - Closed nightly from 9:00 p.m. to 6:00 a.m., Monday, April 10 through Thursday, April 13 (into Friday morning).

LANE CONFIGURATION ON EB SR 210

In August 2022, the EB SR 210 crossover lane was removed, and the traffic was shifted to the newly paved lanes on EB SR 210.


As part of this new transition, crews installed concrete barriers along EB SR 210 from San Bernardino Avenue to the EB/WB I-10 connectors to safely separate travel lanes from adjacent work areas. In this configuration, motorists entering EB SR 210 using the on-ramp at San Bernardino Avenue are not able to access the EB I-10 connector and will be automatically directed onto WB I-10. This configuration will be in place for approximately four to five months. 


EB SR 210 to EB I-10 Suggested Detour: 


  • From San Bernardino Avenue travel south on Tennessee Avenue and turn left onto the EB I-10 on-ramp to access the freeway. 
SOUND WALLS AND RETAINING WALLS

Construction of new sound walls and/or retaining walls is underway throughout the project corridor. This work is ongoing Mondays through Saturdays during daytime hours (6:00 a.m. to 4:00 p.m.) and intermittently during nighttime hours (9:00 p.m. to 5:00 a.m.). 

 

For more information on sound wall and retaining wall construction, please call (877) 55-SBCTA or email info@goSBCTA.com.

ABOUT THE PROJECT

The SR 210 Lane Addition and Base Line Interchange Project is designed to provide increased traffic flow throughout this corridor. To eliminate the existing bottleneck and provide lane continuity, the SR 210 will be widened from Sterling Avenue to San Bernardino Avenue in the cities of San Bernardino, Highland, and Redlands, as well as an unincorporated portion of San Bernardino County. Base Line Interchange will also be widened from Buckeye Street to Seine Avenue in the City of Highland, which will include widening three of the four interchange ramps. As the SR 210 Lane Addition and Base Line Interchange projects aligned geographically and shared similar delivery schedules, they were combined for the design, right-of-way, and construction phases to save cost and expedite the schedule. In addition, pavement rehabilitation work was added through a cooperative agreement with Caltrans that includes new concrete pavement between 5th Street and Lugonia Avenue. Adding the pavement rehabilitation work during the Lane Addition and Base Line Interchange projects means one less project that the community will have to navigate around in the future.


Please remember construction is dynamic and the schedule is subject to change.

Walking on the freeway is unsafe. In case of an emergency, please dial 9-1-1. For non-emergency Freeway Service Patrol (FSP) services, call the California Highway Patrol (CHP) at (909) 428-5400 or use the nearest Call Box for assistance. Drivers or passengers of a disabled vehicle stopped on a freeway may walk to the nearest exit, in either direction, on the same side of the freeway upon which the vehicle is disabled, or to the nearest Call Box for assistance. For the safety of the public and our crews, unapproved access to construction sites and property related to project construction is prohibited.

Sign up for text messages by texting SR210Baseline to (888) 525-1021 (Reply STOP to cancel, text HELP for help. Normal text and data message rates apply.