This week's activities:
What to expect this weekend (1/26-1/27)
Hours of Construction Activity: 7 am - 3:30 pm
Work will occur over the weekend to backfill at the tunnel area on the Packard Expansion site. Oxygen line work will also continue. Excavation and off haul of soil will also continue.
Weekday work (1/28-2/1)
Hours of Construction Activity: 7 am - 5 pm
Oxygen line work will continue next week.
Waterproofing work will also begin at the tunnel area.
Some preparation work to support future pedestrian rerouting inside and outside of the hospitals may begin.
Face cut excavation will continue on the site as well bench cut work at the W wall and excavation activities.
Intermittent dirt off haul will occur from the Packard Expansion site through the end of January.
Utility work will continue near the Stanford Hospital & Clinics side of the Falk Building. Access to the Falk Building will be maintained at all times via the Stanford Hospital side of the building. Pedestrian detour signage is in place.
Access to the rear entrance of Packard Children's will remain open throughout construction.
What to expect next weekend (2/2-2/3)
Hours of Construction Activity: 7 am - 3:30 pm
Excavation, waterproofing and oxygen line work are scheduled to continue next weekend.