March 2012-March 2013
The New Stanford Hospital facility site prep (known as the 'Make-Ready' site) includes surface demolition and utility work on North Pasteur Drive, and the demolition of Parking Structure 3 and 1101 Welch in order to make way for the new hospital facilities.
CCSR Area Construction Update
In order to accommodate patient parking and access to Stanford Hospital & Clinics during construction, the Stanford School of Medicine has afforded SHC temporary use of the area north of the Center for Clinical Sciences Research (CCSR) for valet parking. Accommodating hospital patient parking and decanting the currently used Parking Structure 3 is critical to the success of the new Stanford Hospital construction.
Construction for this temporary parking area is underway. Once completed, 100+ valet cars will be accommodated on this lot.
The New Stanford Hospital project team has been working closely with the Stanford University campus architect to assure that the plans for this temporary parking area meet campus approval and map to the aesthetics of the greater campus community.
This week's activities:
What to expect this weekend (10/13-10/14)
Hours of Construction Activity: 7 am - 7 pm; nighttime work inside of Parking Structure 4 from 10 pm-6 am
Work will occur inside of Parking Structure 4 (PS-4) over the weekend inside the entry at Level 1 of the garage. This work will be noise producing. Ear plugs will be available in the PS-4 lobby.
Electricians will also be working on all levels in PS-4 over the weekend to mount conduits on the walls of the underground parking structure. No noise or dust impacts are expected as part of this effort.
Weekday work (10/15-10/19)
Hours of Construction Activity: 7 am - 4 pm
On Monday, 10/15, an electrical shutdown will occur in PS-4 from 10 am-1 pm to allow for the installation of a new electrical panel. The lighting levels inside of the garage will be significantly decreased during this time. Signage will be in place to inform employees of the work under way.
Construction for the temporary CCSR parking area will continue.
Storm and sewer trenching will continue in North Pasteur Drive near the exit to Parking Structure 3 (PS-3). Access will be maintained out of the garage at all times.
A pedestrian bypass will remain in place on Blake Wilbur Drive between PS-4 and the clinics. An ADA detour will also remain in place.
Construction work to reconfigure Parking Structure 4, the underground employee parking structure, will continue next week.
What to expect next weekend (10/20-10/21)
Hours of Construction Activity: 7 am - 4 pm
No work is scheduled to occur next weekend.
|