December 2012- 2018
Work is under way to construct the new Stanford Hospital facility in order to accommodate advances in medical technology, increase capacity, and meet new seismic safety standards. The 824,000 square foot hospital includes 368 individual patient rooms, state-of-the-art diagnostic and treatment rooms, an expanded Emergency Department, new employee parking structure, five gardens, walking trails and a meditation room. The new hospital is expected to be completed in 2017 and open for patient care in early 2018.
This week's activities:
What to expect this weekend (10/19-10/20)
Hours of Construction Activity: 9 am- 6 pm
Former Garden Entry/D Pod:Utility relocations will continue over the weekend.
New Hospital and Parking Garage: Foundation pile installation will continue for the new hospital facility; foundation work and utility installation will continue for the new parking garage.
Weekday work (10/21-10/25)
Hours of Construction Activity: 7 am - 6 pm: night work will occur on 10/23 near the Garden Entrance to Stanford Hospital & Clinics
Former Garden Entry/D Pod:Utility relocations will continue next week. On 10/23, a utility tie-in will be performed at 3 am near the Garden Entrance to Stanford Hospital & Clinics.
New Hospital and Parking Garage:Foundation pile installation will continue for the new hospital facility; foundation work and utility installation will continue for the new parking garage.
What to expect next weekend (10/26-10/27)
Hours of Construction Activity: 9 am - 6 pm
Former Garden Entry/D Pod:Utility relocation may continue next weekend.
New Hospital and Parking Garage:Construction activity will continue on the new hospital and parking garage sites.
|