August 2011-December 2016
The Packard Children's Hospital expansion, which will expand Packard's ability to care for children and expectant mothers, is under way. The new 521,000 square foot facility will add 150 patient beds, more healing spaces, and the latest medical technology. The Packard expansion is scheduled to open in 2016.
This week's activities:
What to expect this weekend (11/16-11/17)
Hours of Construction Activity: 8:00 am to 6:00 pm
Mat slab #9 concrete placement is scheduled for Saturday morning (12:01am).
No work currently scheduled for Sunday, 11/17.
Weekday work (11/18-11/22)
Hours of Construction Activity: 7:00 am to 6:00 pm; Dirt off-haul as needed 4 pm - 12 am
Construction trailer delivery will continue on Monday, 11/18, at the inboard lane of Quarry Road at Welch from 10.30 am until 3.30 pm.
Rebar installation, waterproofing, concrete formwork, and bench cutting work will continue on the Packard expansion site next week. All work is being closely coordinated with the hospital and is not anticipated to cause noise or vibration. The tower crane will be in use to install rebar columns and formwork.
Dirt off haul will continue during the week as needed between 4 pm and 12 am.
Access to the rear entrance of Packard Children's will remain open throughout construction although some egress detours will be in place.
What to expect next weekend (11/23-11/24)
Hours of Construction Activity: 8:00 am to 6:00 pm
No work currently scheduled to occur next weekend.
|