March 2012-March 2013
The New Stanford Hospital facility site prep (known as the 'Make-Ready' site) includes surface demolition and utility work on North Pasteur Drive, and the demolition of Parking Structure 3 and 1101 Welch in order to make way for the new hospital facilities.
This week's activities:
What to expect this weekend (11/17-11/18)
Hours of Construction Activity: 7 am - 7 pm
No work is scheduled to occur this weekend.
Weekday work (11/19-11/21)*
Hours of Construction Activity: 7 am - 4 pm
*No work will occur over the Thanksgiving holiday
Next week, work will begin to demolish Parking Structure 3 (PS-3), the former patient and visitor parking lot. The parking structure must be removed, followed later this year with the demolition of 1101 Welch Road, in order to make way for the new hospital facilities.
In order to demolish the building, large excavators will be used to take apart the parking garage starting at the top level and crunching the material down to ground level. This process will continue one bay at a time until the structure is completely down. Equipment will be placed on the ground to the west of the garage and work its way inward as each bay is removed.
Machinery and equipment will be delivered to the PS-3 site on Monday, 11/19 at 5 am and demolition work will begin as early as Tuesday, 11/20. This work is expected to take three months to complete. Regular work hours will occur between 7 am and 4 pm. Demolition work will begin closest to the Cancer Center, moving south towards the North Pasteur Drive side of the site.
During demolition activities, there will be noise and vibration near the site. This work will be monitored very closely to help mitigate any impacts inside of the hospital. Infection control measures are in place and will be checked continuously in order to ensure the health and safety of our patients, employees and visitors.
Work in the Promenade will continue including new water line and exit path construction along with ramp and stair installation. The work outside of the fence at the north end toward Wang Plaza should be completed by Wednesday, 11/21.
What to expect next weekend (11/24-11/25)
Hours of Construction Activity: 7 am - 4 pm
No work will occur over the Thanksgiving holiday weekend.
Weekday work (11/26-11/30)*
Hours of Construction Activity: 7 am - 4 pm
All New Stanford Hospital Make-Ready construction activities will continue the week following Thanksgiving unless otherwise noted above.
Truck hauling will begin on Wednesday, 11/28, to off haul demolition material from PS-3.
Work will occur on the second half of the CCSR temporary parking lot pending permits. This work will take three weeks to complete (weather permitting) and require 10 hour shifts six days a week.
|