August 2011-December 2016
The Packard Children's Hospital expansion, which will expand Packard's ability to care for children and expectant mothers, is under way. The new 521,000 square foot facility will add 150 patient beds, more healing spaces, and the latest medical technology. The Packard expansion is scheduled to open in 2016.
This week's activities:
What to expect this weekend (12/7-12/8)
Hours of Construction Activity: 8 am - 6 pm
Rebar installation and site cleanup will continue over the weekend.
Weekday work (12/9-12/13)
Hours of Construction Activity: 7 am - 6 pm; off hours dirt off haul will occur
Rebar installation, waterproofing, concrete formwork, and bench cutting work will continue on the Packard expansion site next week. All work is being closely coordinated with the hospital and is not anticipated to cause noise or vibration.
The tower crane will be in use to install rebar columns and formwork.
Excavation and dirt off haul will continue next week out of the Quarry gate.
Access to the rear entrance of Packard Children's will remain open throughout construction although some egress detours will be in place.
What to expect next weekend (12/14-12/15)
Hours of Construction Activity: 8 am - 6 pm
Rebar installation and site cleanup will continue next weekend on the Packard expansion site.
|