This week's activities:
What to expect this weekend (2/16-2/17)
Hours of Construction Activity: 7 am - 3:30 pm
Concrete pour work will occur on the site over the weekend. A crane will be in use on the construction site.
Off haul of soil will continue over the weekend.
Weekday work (2/19-2/22)*
Hours of Construction Activity: 7am - 5pm
*No work is scheduled to occur on Monday, 2/18, due to the Presidents' Day holiday
Next week, construction crews will continue to off haul dirt from the site.
Soldier piles will be going in near the Falk Building and Packard Children's beginning as early as 2/19. This work is being closely coordinated with the hospital and is scheduled to be completed on 2/28.
Tie back drilling, excavation and shot crete work will also continue next week.
A sewer shutdown is planned for 2/19.
Utility work will continue near the Stanford Hospital & Clinics side of the Falk Building. Access to the Falk Building will be maintained at all times via the Stanford Hospital side of the building. Pedestrian detour signage is in place.
Work will continue in the parking lot of 730 Welch Road to construct a temporary MRI facility.
Access to the rear entrance of Packard Children's will remain open throughout construction.
What to expect next weekend (2/23-2/24)
Hours of Construction Activity: 7 am - 3:30 pm
Work is scheduled to occur on the Packard expansion site next weekend.