September 2012-December 2016
The Packard Children's Hospital expansion, which will expand Packard's ability to care for children and expectant mothers, is underway. The new facility is scheduled to open in 2016.
This week's activities:
What to expect this weekend (4/13-4/14)
Hours of Construction Activity: 7 am - 3:30 pm
Site excavation, soldier pile installation and truck off haul will occur on the expansion site. Auger cast pile drilling will also occur over the weekend.
Weekday work (4/15-4/19)
Hours of Construction Activity: 7 am - 5 pm
Soldier piles will continue to be installed near Packard Children's Hospital next week. This drilling work is being closely coordinated with the hospital and is not anticipated to cause noise or vibration.
Excavation work and off hauling of soil will also occur.
Access to the rear entrance of Packard Children's will remain open throughout construction although some egress detours will be in place.
What to expect next weekend (4/20-4/21)
Hours of Construction Activity: 7 am - 3:30 pm
Work is expected to occur on the Packard Expansion site next weekend.
|