August 2011-September 2013
One of the first steps in the effort to expand Packard Children's Hospital and rebuild Stanford Hospital includes utility work and surface improvements. The Welch Road Utility Project includes: replacing utility services and information technology infrastructure along Welch and Quarry Roads to serve the new hospital facilities once they are built; the widening of Welch Road; replacement of sidewalks, curbs and gutters; planting of new street trees and installation of planted medians and street lighting.
Note: Access to the Emergency Room will be maintained at all times.
This week's activities:
Hot water line work will continue on Welch Road.
The crosswalk across from 730/700 Welch (near the California Caf� parking lot) will move back to its original location across from 750 Welch by end of day on Tuesday, 4/30.
The driveway at 770 Welch will also reopen on 4/30.
The south driveway at 900 Welch Road will be closed on Monday, 4/29. The north driveway to the property will remain open during this time.
The north driveway at 1000 Welch Road will be closed on Monday, 4/29. The south driveway will remain open during this time.
On Tuesday, 4/30, the south driveway at 1000 Welch Road will close. The north driveway will remain open during this time.
Rough grading, paving and sidewalk work on Welch Road will also continue.
Please be cautious of construction trucks entering the road.
What to expect next weekend (5/4-5/5)
Hours of Construction Activity: 7 am - 5 pm