August 2011-September 2013
One of the first steps in the effort to expand Packard Children's Hospital and rebuild Stanford Hospital includes utility work and surface improvements. The Welch Road Utility Project includes: replacing utility services and information technology infrastructure along Welch and Quarry Roads to serve the new hospital facilities once they are built; the widening of Welch Road; replacement of sidewalks, curbs and gutters; planting of new street trees and installation of planted medians and street lighting.
Note: Access to the Emergency Room will be maintained at all times.
This week's activities:
What to expect this weekend (5/12-5/13)
Hours of Construction Activity: 7 am - 3:30 pm; night work on 5/13 beginning at 8 pm until 5 am on Monday 5/14.
Paving work will occur at 777 and 801 Welch. Due to this work, the 801 parking lot will be closed again on Saturday, 5/12.
On Sunday, 5/13, water utility work will continue near the AMC in Blake Wilbur Drive. This work will be performed at night and will require some traffic changes between 8 pm-5 am. Some noise is anticipated from saw-cutting, jack hammering and backhoe equipment. The Marguerite shuttle will maintain service to Blake Wilbur Drive. This work is anticipated to be completed in the next couple of weeks.
Weekday work (5/14-5/18)
Hours of Construction Activity: 7am - 3:30 pm
Welch Rd is now a one-lane, one-way road going West from Quarry to Pasteur Drive. This change will be in effect for two years. We thank you for your patience regarding this significant change and ask that you please adjust your driving route accordingly. South Pasteur Drive is now a two-way two-lane road. North Pasteur Drive is closed between Blake Wilbur Drive and Sand Hill Road.
K-Rail will remain in place on the inboard side of Quarry Rd (between Welch and continuing up to the Quarry Extension near the turn to the Emergency Department) in order to facilitate ongoing utility work. This reduces Quarry to a two lane, two direction road during this time. Access will be maintained to the Emergency Department at all times.
Work will continue to install a new hot water line on Quarry Road. A portion of this work will continue to take place outside of the K-Rail in the quarry Extension. Access to the Emergency Department will be maintained at all times.
At 3 am on Tuesday, 5/15, the City of Palo Alto may perform an interconnect to the existing gas main near 777 and 801 Welch in order to support a future switchover. The K Rail on Welch Road will be moved during this time. Traffic and emergency access will be maintained at all times.
On 5/17, the City of Palo Alto will be onsite to finish pre-switchover electrical work on Welch Road. This work should not impact neighboring properties or the hospitals.
Work on the chilled water line will continue on Welch Rd, moving south.
Please be cautious of construction trucks entering the road. Access to the Emergency Room will be maintained at all times.
Night Work (5/14-5/18) Hours of Construction Activity: 8 pm- 5 am
Water utility work will continue near the AMC in Blake Wilbur Drive. This work will be performed at night and will require some traffic changes between 8 pm-5 am. Some noise is anticipated from saw-cutting, jack hammering and backhoe equipment. The Marguerite shuttle will maintain service to Blake Wilbur Drive. This work is anticipated to be completed in the next couple of weeks.
What to expect next weekend (5/19-5/20)
Hours of Construction Activity: 8am - 5 pm; night work on 5/13 beginning at 8 pm until 5 am on Monday 5/14.
Utility work may occur on Quarry and Welch Roads.
Water utility work will continue near the AMC in Blake Wilbur Drive. This work will be performed at night and will require some traffic changes between 8 pm-5 am. Some noise is anticipated from saw-cutting, jack hammering and backhoe equipment. The Marguerite shuttle will maintain service to Blake Wilbur Drive. This work is anticipated to be completed in the next couple of weeks.