August 2011-September 2013
One of the first steps in the effort to expand Packard Children's Hospital and rebuild Stanford Hospital includes utility work and surface improvements. The Welch Road Utility Project includes: replacing utility services and information technology infrastructure along Welch and Quarry Roads to serve the new hospital facilities once they are built; the widening of Welch Road; replacement of sidewalks, curbs and gutters; planting of new street trees and installation of planted medians and street lighting.
Note: Access to the Emergency Room will be maintained at all times.
This week's activities:
What to expect this weekend (5/18-5/19)
Hours of Construction Activity: 7 am - 5:30 pm; nighttime work on Arboretum Road on Sunday, 5/19 between Sand Hill and Quarry between 9:30 pm-6 am
Dirt will be off hauled from the Pasteur lot over the weekend.
On Sunday, 5/19, evening utility work will occur between 9:30 pm and 6 am requiring the closure of Arboretum Road between Sand Hill Road and Quarry Road. Thru traffic on Sand Hill Road and Quarry Road will not be disrupted. Construction is estimated to take 4-6 weeks to complete.
Weekday work (5/20-5/24)
Hours of Construction Activity: 7 am - 7 pm; nighttime work on Arboretum Road between Sand Hill and Quarry
between 9:30 pm - 6 am
The northern driveway at 900 Welch will reopen on Tuesday morning, 5/21, by 7 am. The southern driveway at 900 Welch will then close for approximately two weeks in order to accommodate site work at the property. Partial driveway closures will also continue at 1100 Welch Rd.
Rough grading, paving, curb, gutter and sidewalk work on outboard Welch Road will continue.
Evening utility work will occur between 9:30 pm and 6 am requiring the closure of Arboretum Road between Sand Hill Road and Quarry Road. Thru traffic on Sand Hill Road and Quarry Road will not be disrupted. Construction is estimated to take 4-6 weeks to complete.
The driveways at 1000 Welch Road will be controlled by flagger during the day on Friday, 5/24. At 7 pm on 5/24, the driveways will close and reopen at 6:30 am on Monday, 5/27 (Memorial Day). No vehicular access will be available to the property during this time.
Please be cautious of construction trucks entering the road.
What to expect next weekend (5/25-5/26)
Hours of Construction Activity: nighttime work on Arboretum Road between Sand Hill and Quarry between 9:30 pm-6 am
The driveways at 1000 Welch Road will be closed to all vehicular traffic over Memorial Day weekend. The driveways will reopen at 6.30 am on Monday, 5/27 (Memorial Day).
|