August 2011-October 2012
The Packard Children's Hospital expansion site prep (known as the 'Make-Ready' site) includes the demolition of 701 & 703 Welch and the construction of a shoring wall and utility tunnel in preparation for the Packard Children's expansion.
This week's activities:
Weekend work (9/23-9/25): day shift: 7 am- 4 pm; night work: 8 pm-5 am
Preparatory utility-related work will continue on Quarry Rd in the evenings. Traffic control measures will be in place. Please be cautious of trench plates in road. Access to the Emergency Room will be maintained at all times.
Weekday work (9/26-9/30): 7 am-4 pm
Abatement will continue at 703 and 701 Welch in preparation for building demolition next month. Construction of a new sidewalk on the east side of the Falk building continues with asphalt now expected mid-week. No equipment causing vibration will be used. Once completed, Falk Lot bicycle racks and lockers will be relocated on the property, most likely at the end of the month. The racks and lockers will be posted prior to moving. The sidewalk installation along the north and east side of Packard Hospital, near the Bass Center, is complete.
Permits pending, work will begin to relocate the chilled water line adjacent to 703 Welch and Packard Children's Hospital. This work includes some excavation work to install new water lines and may include noise-producing activities.
On 9/28, a crane will arrive at the Make Ready site to facilitate the relocation of trees.
Night work (9/19-9/30): 8 pm-5 am
Preparatory utility-related work will continue on Quarry Rd. Traffic control measures will be in place. Electrical work is scheduled to begin on Quarry beginning 9/26. This work includes digging a trench across Quarry Rd during night shifts only. Please be cautious of trench plates in the road. Access to the Emergency Room will be maintained at all times. Some tree relocation work is scheduled to occur on the Make Ready site next week in the evening hours. This work may cause some noise and vibration.
What to expect next weekend (9/30-10/2)
Abatement work will continue at 703 and 701 Welch Rd.
Some tree relocation work is scheduled to occur on the Make Ready site. This work may cause some noise and vibration. Preparatory utility-related work will occur on Quarry Rd in the evenings. Traffic control measures will be in place. Please be cautious of steel plates in road. Access to the Emergency Room will be maintained at all times.
|