We are currently working on multiple projects in Bennington. This is the first contract we signed with the Town of Bennington for their water system remedial expansion, which involves Houghton Lane and the surrounding roads.
- Start Date: July 2019
- Scheduled Completion Date: August 2020
- Project Manager: Jeff Chase
- Superintendent: Zack Thompson
- Foremen: Seth Widli, Brian Rossier, Jeff Gokey
The team is installing a new water system including water main, services, asphalt paving, concrete walkways, abandonment of existing water wells, and restoration.
This work is important to Bennington's critical infrastructure due to the widespread PFOA (man-made chemical used in industrial processes) ground/water contamination that has been found in the area. Our work will help connect residents to municipal water sources, meaning clean drinking water for the community.