May Construction Update

Crosswalk Work on Appian Way

Starting as early Wednesday, May 27, through Friday, May 29, crews will perform daytime work along Appian Way between Seaside Terrace and Moss Avenue and at Ocean Avenue to remove and restripe the crosswalks at each intersection. This work will require intermittent partial closures of the roadways. Access will be maintained by a flagger during the operation.

A Fresh Way to Experience the Santa Monica Pier Arrives June 5

Starting Friday, June 5, visitors heading to the Santa Monica Pier will be welcomed by a temporary pedestrian bridge that will serve as the primary entrance throughout construction of the the bridge connecting Ocean Avenue to the Pier.


While the access route is shifting approximately 30 feet south, the Pier will remain fully accessible during construction, with all restaurants, shops and attractions remaining open.


Designed to maintain a convenient access through the end of construction in late 2027, the temporary bridge also creates a fun and colorful arrival experience featuring eye-catching artwork, wayfinding elements and spotlights on local businesses.


Additional Pier access points will remain available from:



  • Ocean Front Walk
  • The protected walkway along the temporary vehicle ramp in the Pier parking lot
  • Stairs near Bubba Gump Shrimp Co.


Following the opening of the temporary bridge, crews will close the current entrance facing Ocean Avenue and will begin to prepare the existing bridge for demolition.


Bikes, skateboards and other small vehicles will not be permitted on the temporary pedestrian bridge, they will be advised to use Seaside Terrace to access the Pier.


The City appreciates the continued patience and support from visitors, businesses and the community as this important improvement project moves forward.

Pier Bridge Demolition This Summer

Starting the week of June 8, crews will begin preliminary work to prepare for demolition of the Pier bridge. Demolition is anticipated to begin the week of June 15 and will continue for two to three months.


Crews will begin work near Appian Way and continue toward the Pier, then they will return to Appian Way and progress in the opposite direction toward Ocean Avenue. Construction work will occur during daytime hours between 5 a.m. and 1:30 p.m.


This work will require temporary closures of the Moomat Ahiko Way, Appian Way and portions of Ocean Front Walk. Detour signage will be posted to help direct vehicles and pedestrians around the work area.


Access to the Pier and surrounding businesses will remain available during construction. Separate coordination efforts will take place with Pier and Ocean Front Walk Businesses in advance of any closures.

Longterm Appian Way Closure Later this Summer

An eight-day closure of Appian Way is anticipated to occur in mid-July to accommodate bridge demolition activities over the roadway. During the closure, vehicles will not be able to access the Pier parking lot from Appian Way. Access to Pier parking will be maintained from PCH.


During the closure, drivers will be directed to use the following parking lots:




Additional details will be shared as they become available.

Temporary Vehicle Ramp to Remain Open During Construction

During construction, emergency and delivery vehicles must enter through the Pier parking lot and follow the designated route to the temporary ramp. Please see below for access route.

Palm Tree Relocation

Crews will temporarily remove and relocate a row of palm trees within the construction zone in preparation for the demolition and reconstruction of the Santa Monica Pier Bridge.Work will be conducted in coordination with a certified arborist and biologist to help ensure proper handling and minimize impacts where possible.

Construction schedules are subject to change. Please visit the project website at www.santamonica.gov/pierbridge for the most up-to-date work schedules.

Construction Activity and Closure Information

An interactive "Construction Activity and Closure Information Map" is updated regularly highlighting major activities and associated closures and detours. Click on the image to learn mor.

Construction schedules are subject to change. Please visit the project website at www.santamonica.gov/pierbridge for the most up-to-date work schedules.