Office: 843.671.1343
Sea Pines Security: 843.671.7170
CSA Maintenance: 843.671.7849
www.SeaPinesLiving.com | Facebook: www.facebook.com/SeaPinesLiving
In this message
  • Updates from the Sea Pines CSA Maintenance Department
  • Greenwood Drive Reconstruction Project Update
  • Sea Pines Drive Timber Bridge Project Update
  • CSA & ASPPPO Board of Director Election Information
  • Save the Date
  • December 5th-Community Coffee (Webinar Registration Link Provided)
  • December 11th-Property Owner Holiday Open House
  • CSA Administration Office Holiday Hours
Project Updates From the Sea Pines CSA Maintenance Department
Greenwood Drive Reconstruction Project Update

Work Continues In Phase One Greenwood Drive Reconstruction Project Area

The Phase One Project area of Greenwood Drive from Club Course Drive to Governors Road remains an active work zone. Please be reminded that the speed limit on Greenwood Drive is 35 MPH.

As noted in our communication on Nov. 3 ( view here ) construction activities will continue on or near Greenwood Drive and some leisure trails within the phase one project zone into early 2019, weather permitting.
The reconstructed portion of Greenwood Drive (Club Course Drive to Governors Road) was engineered and designed to South Carolina Department of Transportation standards based on the level of service for a 35 MPH roadway.

At this time, the roadway has been not been accepted as a completed project and remaining work to occur on or near the roadway/ leisure trails includes:
  • Additional construction work
  • Road and Leisure trail paving
  • Permanent line striping
  • Raised roadway reflector installation
  • Stamping crosswalk connecting the leisure trail from Lot 3 to the Forest Preserve parking lot
  • Sign installation
  • Landscaping
  • Roadside soil grading
  • Turf and Irrigation installation
  • Mulch and pine-straw application
  • Site clean up
  • Seeding of the trolley lots

Sea Pines property owners, guest and visitors may experience temporary flagging operations, traffic cones and delineators placed along the roadway, crews and equipment working along the roadway and temporary lane closures during these remaining construction activities.

We are in constant communication with our Engineer and our contractor regarding the project, quality control and the outstanding punch list of items to be completed, including the correction of some areas of imperfections in the new roadway surface. Full acceptance of this roadway will not occur until these punch list items are addressed and the Engineers certification is received, which will then initiate the warranty period.

Phase One Project Area Status Updates:
  • Roadside soil grading is in process in this area
  • Mulching is underway in this area 
  • The permanent line striping of this area has been rescheduled, a new date has not been determined. We will communicate the new date once it is set. 

We appreciate your patience as we continue to work to complete these important infrastructure repairs and replacements. If you have questions regarding this project, please contact the Sea Pines CSA Maintenance Department at 843.671.7849 or by email at csamaintenance@csaseapines.com .
Sea Pines Drive Timber Bridges Project Update
Sea Pines Drive Timber Bridges Now Open

The newly constructed pedestrian timber bridges spanning over the canal on South Sea Pines Dr. connecting the existing leisure trail to Beach Walk 25 (located between Snowy Egret and Black Skimmer) and Beach Walk 26 (located between Surf Scoter and Snowy Egret), as well as the reconstructed pedestrian bridge located on Greenwood Drive near the Sea Pines Drive intersection are now open.

These bridges are open, but these areas remain an active work zone . Remaining items to be addressed:
  • Completing the installation of the stainless steel cabling
  • Painting of the bridges
  • Completing details on the crosswalk stamping
  • Seeding the lawns adjacent to the bridges
  • Site clean-up and completing some asphalt work

For questions regarding this project, please contact the Sea Pines CSA Maintenance Department at 843.671.7849 or by email at csamaintenance@csaseapines.com .
Have You Returned Your Board of Director Election Ballot?
CSA and ASPPPO Board of Director Election Information
  • Ballots were mailed out on November 1, 2018.
  • Ballots must be postmarked for return by Dec. 1, 2018.
  • Ballots are distributed via postal mail and cannot be emailed.
  • If you need a replacement ballot, please email us at election@seapinescsa.com. Please include your first and last name, Sea Pines Property address and the mailing address in which you wish to receive your replacement ballot. Please allow 3-5 business days for your mailed replacement ballot to arrive.

Click here to learn more about each of the candidates.
Click here to view the Meet the Candidates Forum webinar video.
December Community Coffee
Wednesday, December 5
9:00 AM - 10:30 AM
Sea Pines Community Center
71 Lighthouse Road Suite #120

For those not able to attend in person, join us via webinar. Click here to register for the meeting webinar.
Property Owner Holiday Open House
Sea Pines Property Owner
Holiday Open House
Tuesday, December 11
3:00 PM-6:00 PM
Tower Beach

All Sea Pines Property Owners are cordially invited to come out to meet and greet with your neighbors! Enjoy light hor d'oeuvres, beer and wine.
Reservations not required

Parking at Tower Beach is limited, overflow parking will be provided at Parcel One near Land's End with trolley service to Tower Beach.
CSA Administration Office Holiday Hours
These hours apply to the CSA Administration Office only:

Closed at 12 noon today November 21
Closed: Thursday, November 22 and Friday, November 23

We will return to normal business hours on Monday, November 26 - 7:30 AM - 4:30 PM

Wishing everyone a safe and Happy Thanksgiving!
Sea Pines Community Services Associates 
843.671.1343 | Info@csaseapines.com | www.SeaPinesLiving.com