Area 1: Reston Avenue to Colvin Forest Drive (Except Baron Cameron Avenue Intersection)
- Completed noise barrier foundations along westbound Route 7 near Great Passage Boulevard.
- Completed noise barrier post and panel installation along eastbound Route 7 between Bishopsgate Way and Markell Court, and along westbound Route 7 between Amanda Drive and Great Passage Boulevard.
- Continued noise barrier post and panel installation along eastbound Route 7 between Reston Parkway and Bishopsgate Way.
- Continued surface paving and pavement markings on westbound Route 7 between Colvin Run Road (west) and Amanda Drive.
- Continued surface paving and pavement markings on eastbound Route 7 from Markell Court to east of Delta Glen Court.
Area 2: Baron Cameron Avenue Intersection
- Completed surface paving on Route 7 at the Baron Cameron Avenue intersection.
- Completed the third-lane widening on westbound Baron Cameron Avenue, providing additional capacity through the traffic signal at Hunter Gate Way.
Area 3: Difficult Run Area (Colvin Forest Drive to Faulkner Drive
- Completed curb and gutter installation along eastbound Route 7 between Colvin Forest Drive and Serenity Woods Lane.
Area 4: Faulkner Drive to Jarrett Valley Drive
- Completed noise barrier foundations along eastbound Route 7 between Trap Road and Wolftrap Run Road.
- Continued surface paving and pavement markings on eastbound Route 7 between Trap Road and Jarrett Valley Drive.
- Started surface paving on westbound Route 7 between Jarrett Valley Drive and Lewinsville Road.
- Began construction of the new service road between Wolftrap Run Road and McLean Bible Church.
- Continued construction of the permanent configuration of the Lewinsville Road intersection.
Project-Wide
- Third-party utility relocation activities are ongoing.
- Continued grading, placement of stone and paving for the shared-use paths.