River North Lighting Project
The Chicago Department of Transportation (CDOT) has completed new light pole installation in the area bounded by Chicago, Ontario, Orleans, and the River. CDOT has begun removal of the old light poles and continues to restore infrastructure trenching.
Helicopter Lift - 111 N Canal
On Saturday, January 11, from 9am to 11am, there will be a helicopter lift at 111 N Canal Street. During the lift, Washington, from Canal to Wacker will be closed to vehicular and pedestrian traffic.
157 W Grand Ave
On Saturday, January 11, 2025 a crane lift will take place to replace two units on the rooftop of 157 W Grand, resulting in a partial street closure from 8am - 5pm. One lane will remain open on Grand Ave during the lift. A backup day will be scheduled for Sunday, January 12, 2025.
Pin & Link Project on Randolph and Columbus
CDOT crews are scheduled to perform steel work and bridge expansion joint rehab along Randolph Street, Columbus Drive, and Stetson Avenue. Please see details below:
General Construction Schedule:
7:00 am - 3:30 pm, Monday - Friday; with the occasional extension to 5:30 pm as needed.
Scope of Work and Access Impacts During Construction:
In general, one lane of travel will be open at all times along each roadway, level, and direction. Access along sidewalks will remain open with detours around the work areas.
This project is expected to be completed at the end of June 2025. Asphalt restoration will occur in July 2025.
Casino Demolition Update
The demolition team will begin site concrete crushing operations over the next eight weeks. The operation with run from 8 AM until 5 PM. The crusher will be placed in between the Ontario feeder ramp and the southern edge of the current building.
|