Daytime water shutoff on Monday
Glenwood Avenue closed at Smith Well Road on Monday and Tuesday
Residents will have access to properties
Smith Well Road will be an active construction zone next week. All work is scheduled for daytime.
-
Water shutoff – 9 a.m. to 5 p.m. Monday, Aug. 26. During this time, crews will install a water main across Glenwood Avenue to Smith Well Road.
-
Glenwood Avenue closure at Smith Well Road – 7 a.m. to 6 p.m. Monday, Aug. 26, and Tuesday, Aug. 27. Utility work will occur in the intersection, followed by temporary trench paving. Traffic will be detoured around the work site via Horne Street and Glencrescent Avenue.
- Sewer maintenance hole excavations and installation – Wednesday, Aug. 28, and Thursday, Aug. 29. This work will occur on Smith Well Road.
- No work is scheduled for Friday, Aug. 30.
Forwarded this email? To sign up, visit https://bit.ly/dovernewsletters and add “Project update: Smith Well water tank and utility work” to your current email subscription list.