In progress: Stanislaus County Courthouse - Modesto, CA
Project Executive: Mark Thompson
Superintendent: Josh Cullum
General Foreman: Antonio Samaniego & Brian Dow
General Superintendent: Kyle Ensminger
Project Manager: Cameron Crocker
Jr. Project Manager: Marissa Souza
CAD/BIM Designers: Elizabeth Anderson, Miguel Jimenez,
and Gerald Tinaza
Lead Estimator: Adam Jautaikis
General Contractor: McCarthy Building Companies, Inc.
Estimated completion date: December 2024
General description: The New Modesto Courthouse project is the building construction and associated site development of a new trial court facility comprised of 27 courtrooms, accommodating approximately 350 judges and court support staff. The building will have 10 floors with basement parking and mechanical roof levels included. The building will be roughly 309,000 square feet and 135 feet high, being the second tallest building in Modesto.
Corporate VDC/BIM Manager Elizabeth Anderson was the lead designer that completed all of the modeling for coordination. The images below are of the basement overhead coordinated model and the installation drawings that were sent to the field. All the circles represent threaded rod that is inserted using blue bangers in the concrete deck above (Tower - Level 1 Deck). All the overhead conduit, lights, and strut racks were coordinated with all the other trades on the project using the cloud platform Revizto. Once fully coordinated, the Design department creates the Trimble installation drawings for the field to use. The Tower-Level 1 Deck has about 1200 points that will be laid out by the field team using the Trimble Total Station.
|