The construction team worked closely with the U.S. Army Corps of Engineers to stabilize construction areas and protect the adjacent waterways from the effects of stormwater run-off. On May 25, 2016 crews returned to work and since then have completed the placement of the embankment to raise the elevation of the new northbound roadway to match the southbound side. The roadway was raised to change the vertical curve and increase the sight distance as required by FDOT's new design criteria. This change improves safety by increasing the distance drivers can see ahead of the vehicles.
Now that the embankment is compete, crews will complete the excavation of the stormwater ponds, grading of the median, shoulders, stabilized subgrade, base and placement of asphalt on the new roadway. All work on this segment of the project is slated for completion late 2016.
|