Center Infrastructure Improvement Project Newsletter

Two-Week Construction Look-Ahead

As work continues in West Hartford Center, the following construction activities

are anticipated along Farmington Avenue over the next two weeks.


November 16, 2026 – November 20, 2026

Farmington Avenue


Phase 8

  • Prepare and pour concrete sidewalks
  • Install streetlight bases and underground conduits
  • Pave along the gutter line
  • Prepare and pave driveway entrances
  • Install brick pavers to join new walkway and driveway apron
  • Install tree root barriers
  • Install remaining fixtures
  • Clean the work area, remove protective coverings, and reopen the completed area


Phase 4B

  • Remove the existing traffic signal mast arm foundation
  • Prepare and pour concrete for the new traffic signal mast arm foundation


Additional Information

  • Continue tree placement throughout the project area
  • Continue electrical conduit work as materials become available
  • Await delivery of signage and materials for temporary pavement markings


November 23, 2026 – November 27, 2026

Farmington Avenue


  • Complete remaining punch list items along Farmington Avenue
  • Clean and clear the laydown area
  • Remove and return temporary barriers and excess fencing to the Town


LaSalle Road

  • Complete remaining punch list items
  • Continue electrical conduit work as materials become available


The project phasing plan has been updated. View the revised schedule here.

Thank You!

As the project nears completion, we would like to extend our sincere gratitude to the businesses of West Hartford Center for your partnership, open communication, and active participation throughout the construction process.


Your willingness to engage with the project team, share feedback, and collaborate on solutions has been instrumental in helping us keep the community informed and minimize impacts whenever possible. We greatly appreciate your patience, flexibility, and continued support as we worked together through each phase of construction.



Thank you for helping make this project a success and for your commitment to the vibrancy and continued growth of West Hartford Center.

Hard Hats Meet Hashtags

 

For photos from the West Hartford Center Project, follow along on Instagram. Stay informed about ongoing work, business highlights, and what’s next for the project!

Stay Informed: Sign Up for Text Alerts

Community members and business owners can opt in to receive SMS text alerts for time-sensitive West Hartford Center Construction Project updates, including traffic impacts and schedule changes. Enroll and stay informed throughout construction.

 
 

ATTENTION: Local Businesses - Get the Business Toolkit

Signage to Help Keep Your Business and Customers Informed!

In this Toolkit:

  • Business Rack Cards - Tips
  • Business Placards - Click the link below to see customized window and/or cash wrap signage for your industry!

If you need additional copies of outreach materials, such as window signs, or have any questions, please feel free to contact us at CenterConstruction@westhartfordct.gov — we’re happy to assist.

The Retail Validation Program:

A Reduced Rate Employee Parking Option for Your Staff

As construction progresses, we're working to maximize on-street parking for customers and visitors. To help, we encourage employees to use alternative parking options, including the Town Center Parking Garage, which offers reduced rates for retail and restaurant employees working in the Center.


The Town Center Garage rates are far lower than other options! The rates are $4.50 for up to an 8.5-hour shift and $7 for anything over 8.5 hours.


For more information, contact Kristen Gorski, Economic Development Manager, at kristen.gorski@westhartfordct.gov.

 

Stay Informed and Ahead of the Curve

For the latest updates and important information about the project, visit our project webpage. It’s your go-to resource for all the news, timelines, and tools to help your business navigate the construction period smoothly.

Have questions or feedback? We’re here to help—email us at CenterConstruction@westhartfordct.gov