Construction Look Ahead

Construction activities remain weather dependent. Below is a preview of scheduled work in West Hartford Center over the next two weeks.

Feb. 23 Feb. 27 (Weather Dependent)

Farmington Avenue (Walden Street to Dale Street)

  • Gerber will continue installation of soil cells.
  • Electrical Contractor is on call to install conduits through newly installed soil cells for future street lighting.

LaSalle Road

  • Electrical Contractor will return to complete remaining electrical work.


March 2 – March 6 (Weather Dependent)

Farmington Avenue (Walden Street to Dale Street)

  • Soil cell installation will continue heading east toward Dale Street.
  • Electrical Contractor will remain on call to install conduits for street lights within newly installed soil cells.

Farmington Avenue (Main Street to Chipotle)

  • A second crew will mobilize to begin work along Main Street to Chipotle (966 Farmington Avenue).

Project Updates

Tree removal was successfully completed on the morning of Tuesday, Feb. 17. As seen previously on LaSalle Road, new trees will be planted using an innovative soil cell system designed to support healthier root growth while protecting sidewalks and infrastructure from future damage.


This approach allows for a greater number of trees and promotes long-term sustainability in the Center.

Stay Informed: Sign Up for Text Alerts

Community members and business owners can opt in to receive SMS text alerts for time-sensitive West Hartford Center Construction Project updates, including traffic impacts and schedule changes. Enroll and stay informed throughout construction.

ATTENTION: Local Businesses - Get the Business Toolkit

Signage to Help Keep Your Business and Customers Informed!

In this Toolkit:

  • Business Rack Cards - Tips
  • Business Placards - Click link below to see customized window and/or cash wrap signage for your industry!

If you need additional copies of outreach materials, such as window signs, or have any questions, please feel free to contact us at CenterConstruction@westhartfordct.gov — we’re happy to assist.

Hard Hats Meet Hashtags

For regular updates and photos from the West Hartford Center Project, follow us on Instagram. Stay informed about ongoing work, progress, and what’s next for the project.

The Retail Validation Program:

A Reduced Rate Employee Parking Option for Your Staff

As construction progresses, we're working to maximize on-street parking for customers and visitors. To help, we encourage employees to use alternative parking options, including the Town Center Parking Garage, which offers reduced rates for retail and restaurant employees working in the Center.


The Town Center Garage rates are far lower than other options! The rates are $4.50 for up to an 8.5-hour shift and $7 for anything over 8.5 hours.


For more info, contact Kristen Gorski, Economic Development Manager, at kristen.gorski@westhartfordct.gov.

Stay Informed and Ahead of the Curve

For the latest updates and important information about the project, visit our project webpage. It’s your go-to resource for all the news, timelines, and tools to help your business navigate the construction period smoothly.

Have questions or feedback? We’re here to help—email us at CenterConstruction@westhartfordct.gov