Center Infrastructure Improvement Project Newsletter

Project Updates

Work in Phase 2A is progressing steadily, with construction crews continuing to make consistent headway on planned improvements. The project remains on schedule, and visible changes are beginning to take shape throughout the area.


Meanwhile, Phase 3B is preparing to enter a more active phase, with work ramping up later next week.

Project Look-Ahead


Construction activities continue to progress throughout the project area. Below is a summary of recent work completed and a look ahead at what’s scheduled for the coming weeks:


8/4/25 to 8/8/25


Phase 2-A

  • Pour sidewalk.
  • Midweek (8/6/25): Remove driveway at Jos A. Banks.
  • End of week: Demo remaining pavers along building frontage.
  • Pour new concrete driveway at Jos A. Banks once formwork is complete.

Phase 2-B

  • Install curb and pour sidewalks at driveway between Beckers and Union Kitchen.
  • Prep for any adjustments needed to access/egress during construction.

Phase 1-A

  • Install curb and pour sidewalks at Post Office driveway.
  • Maintain temporary pedestrian access during work.

Phase 3-B

  • Set up work zone in Phase 3-B.
  • Install traffic control and construction fencing as needed.


8/11/25 to 8/15/25


Phase 2-A

  • Pour remaining sidewalks along building frontage in Phase 2-A.
  • Finalize surface treatments and clean-up in this area.


Phase 3-B

  • Begin demo of pavers and sidewalk in Phase 3-B.
  • Install Silva Cells and subgrade materials.
  • Begin curb installation in Phase 3-B.
  • Coordinate any parking or pedestrian detours with nearby businesses.

Phase 3-A

  • Set up work zone in Phase 3-A
  • Install traffic control and construction fencing as needed.


🌳✨ We're excited to announce that new street trees are coming to West Hartford Center late this fall!   🌳 Street trees play a big role in making West Hartford Center a greener, cooler, and more inviting place! They provide essential shade, improve air quality, enhance natural beauty, and help manage stormwater.  🌿 These benefits support the Town’s goal to preserve open space and create a comfortable, welcoming environment—especially on hot summer days.

Phase 2A

Phase 2B

Blue Mercury

William Raveis

Iris Photo

Webster Bank

Bridgewater Chocolate

Becker's Diamonds & Fine Jewelry

Green Tails Market

Union Kitchen

Lil' Hope


Penzey's


Jos A Bank


Savoy Pizzeria & Craft Bar


Shish Kebab House of Afghanistan


Friendly Toast


In the News

CT Insider recently published an article highlighting construction progress in West Hartford Center, including ongoing work along LaSalle Road as part of a $10 million upgrade. Improvements include new sidewalks, wider pedestrian areas, and the installation of soil cells to support 52 new trees replacing 36 removed earlier this year. The project also features new street furniture and two upcoming mobility hubs to support multimodal transportation.

ATTENTION: Local Businesses - Get the Business Toolkit

Signage to Help Keep Your Business and Customers Informed!

In this Toolkit:

  • Business Rack Cards- Tips
  • Business Placards- Click link below to see customized window and/or cash wrap signage for your industry!

If you need additional copies of outreach materials, such as window signs, or have any questions, please feel free to contact us at CenterConstruction@westhartfordct.gov — we’re happy to assist.

As construction progresses, we're working to maximize on-street parking for customers and visitors. To help, we encourage employees to use alternative parking options, including the Town Center Parking Garage, which offers reduced rates for retail and restaurant employees working in the Center.


The Town Center Garage rates are far lower than other options! The rates are $4.50 for up to an 8.5-hour shift and $7 for anything over 8.5 hours.


For more info, contact Kristen Gorski, Economic Development Coordinator, at kristen.gorski@westhartfordct.gov.

Parking Information for Employees During Construction

Stay Informed and Ahead of the Curve

For the latest updates and important information about the project, visit our project webpage. It’s your go-to resource for all the news, timelines, and tools to help your business navigate the construction period smoothly.

Have questions or feedback? We’re here to help—email us at CenterConstruction@westhartfordct.gov