Center Infrastructure Improvement Project Newsletter

Two-Week Construction Look-Ahead

As work continues in West Hartford Center, the following construction activities are anticipated along Farmington Avenue over the next two weeks.


September 8-11


Phase 6B

  • Complete installation of soil cells.
  • Perform surface demolition at the driveway island.
  • Prepare for and install granite curb at the Westfield Bank driveway.
  • This work will occur early in the week during early-morning hours; driveway access will be limited or restricted while work is underway.
  • Set handholes, valves, and frames to final grade.
  • Remove sidewalk pavers in front of businesses.
  • Form and pour new sidewalks in front of businesses.
  • Outreach staff will notify affected businesses of the confirmed concrete-pour schedule as soon as it is available.



Phase 7

  • Install granite curb along the roadway and at driveways.
  • Continue installing handholes, light bases, and drainage structures.
  • Place processed base and prepare for granite installation.
  • Sawcut concrete at the Eversource vault.
  • Remove sidewalk pavers in front of businesses.
  • Form and pour new sidewalks in front of businesses.
  • Outreach staff will notify affected businesses of the confirmed concrete-pour schedule as soon as it is available.

LaSalle Road

  • Complete bench installation.
  • Begin pavement repair work from Farmington Avenue to Arapahoe Road. Travel will be maintained using alternating one-way traffic during this operation. Pavement repair work is anticipated to take place on Friday.


September 14-18


Phase 4B

  • Complete surface demolition.
  • Place processed base and prepare for granite installation.
  • Excavate for and install catch basins and pipe.
  • Prepare for granite curb installation.
  • Install power bases.


Phase 6B

  • Continue forming and pouring sidewalks.
  • Pave the gutter line.
  • Install weed barrier and topsoil, and protect tree pits.


Phase 7

  • Complete surface demolition at the Bruegger’s Bagels corner.
  • Excavate for and install light pole bases.
  • Place and fine-grade processed base.
  • Complete concrete placements.


Please note: In preparation for sidewalk pours in front of businesses, Gerber will remove pavers and install temporary processed aggregate/stone-dust walkways for pedestrians.


Every effort will be made to minimize disruption and maintain safe access to businesses throughout construction. All activities are weather-dependent and schedules are subject to change.

The project phasing plan has been updated. View the revised schedule here.

Business Spotlights

From longtime favorites to new neighborhood additions, get to know the businesses that add to West Hartford’s character, charm, and sense of community.

Daswani Clothiers

959 Farmington Avenue



For more than 40 years, Daswani Clothiers has been helping customers look and feel their best through exceptional menswear, personalized service, and expert tailoring. Located at 959 Farmington Ave. in West Hartford Center, the family-owned clothier offers a thoughtfully curated selection of suits, sport coats, shirts, trousers, shoes, outerwear, and accessories from leading designers. Whether you’re dressing for a special occasion, refreshing your wardrobe, or looking for a custom-made garment, Daswani’s experienced team provides one-on-one styling and custom tailoring to create a look that feels uniquely yours. The store also offers tailoring, reweaving, and clothing repair services, making it a trusted destination for quality craftsmanship and timeless style.


https://www.daswani-clothiers.com/

The Toy Shop

967C Farmington Avenue


Looking for a little more fun in your day? The Toy Shop WeHa is West Hartford’s neighborhood toy store, offering a thoughtfully curated selection of toys, games, books, and gifts for all ages. From LEGO and building sets to plush animals, craft kits, puzzles, and family game-night favorites, the store has something to spark imagination and bring people together. Located at 967C Farmington Ave. in West Hartford Center, The Toy Shop is a wonderful place to discover a special gift, find a new favorite game, or simply enjoy a little playtime.


 https://thetoyshopweha.com/

Hard Hats Meet Hashtags

For photos from the West Hartford Center Project, follow along on Instagram. Stay informed about ongoing work, business highlights, and what’s next for the project!

Stay Informed: Sign Up for Text Alerts

Community members and business owners can opt in to receive SMS text alerts for time-sensitive West Hartford Center Construction Project updates, including traffic impacts and schedule changes. Enroll and stay informed throughout construction.

ATTENTION: Local Businesses - Get the Business Toolkit

Signage to Help Keep Your Business and Customers Informed!

In this Toolkit:

  • Business Rack Cards - Tips
  • Business Placards - Click the link below to see customized window and/or cash wrap signage for your industry!

If you need additional copies of outreach materials, such as window signs, or have any questions, please feel free to contact us at CenterConstruction@westhartfordct.gov — we’re happy to assist.

The Retail Validation Program:

A Reduced Rate Employee Parking Option for Your Staff

As construction progresses, we're working to maximize on-street parking for customers and visitors. To help, we encourage employees to use alternative parking options, including the Town Center Parking Garage, which offers reduced rates for retail and restaurant employees working in the Center.


The Town Center Garage rates are far lower than other options! The rates are $4.50 for up to an 8.5-hour shift and $7 for anything over 8.5 hours.


For more information, contact Kristen Gorski, Economic Development Manager, at kristen.gorski@westhartfordct.gov.

Stay Informed and Ahead of the Curve

For the latest updates and important information about the project, visit our project webpage. It’s your go-to resource for all the news, timelines, and tools to help your business navigate the construction period smoothly.

Have questions or feedback? We’re here to help—email us at CenterConstruction@westhartfordct.gov