Center Infrastructure Improvement Project Newsletter

Two-Week Construction Look-Ahead

As work continues in West Hartford Center, the following construction activities are anticipated along Farmington Avenue over the next two weeks.


July 13 – July 17

Phase 4

  • Remove existing concrete near storefronts
  • Prepare and install the stone base for future sidewalk and roadway work
  • Fine-grade work areas to prepare for the next stage of construction
  • Complete storm drainage work, including catch basin and manhole modifications and pipe installation
  • Temporarily cover existing pavement markings in preparation for upcoming traffic pattern changes


Phase 5

  • Prepare and install the stone base near storefronts
  • Fine-grade work areas
  • Remove existing pavement along LaSalle Road
  • Excavate, install, and backfill an underground electrical conduit crossing beneath Farmington Avenue


Phase 2B (From Chase Bank to corner of North Main Street)

  • Remove existing pavement and surface materials
  • Prepare for and install granite curbing


Additional Work

  • A&J will continue granite installation and concrete sidewalk work
  • ETC will complete conduit work and remove existing fixtures after the necessary Eversource disconnection is complete


July 20 – July 24

Phase 4

  • Remove existing concrete near storefronts
  • Prepare and install the stone base for future sidewalk and roadway work
  • Fine-grade work areas to prepare for the next stage of construction


Phase 5

  • Install root barriers and topsoil within tree planting areas
  • Prepare and pave the roadway gutter line


Additional Work

  • A&J will continue concrete sidewalk work, saw-cutting, and sealing joints around newly installed granite
  • ETC will install new fixtures and electrical cabinets.


Please note: All activities are weather dependent.

View the updated project phasing plan here to see when construction is expected in each section of Farmington Avenue.

Business Spotlights

From longtime favorites to new neighborhood additions, get to know the businesses that add to West Hartford’s character, charm, and sense of community.

Music & Arts

989 Farmington Avenue



Located at 989 Farmington Avenue in the heart of West Hartford Center, Music & Arts is a one-stop destination for musicians of every age and skill level. Whether you're purchasing your first instrument, renting equipment for school band or orchestra, scheduling music lessons, or in need of expert instrument repairs, their knowledgeable team is ready to help.


With personalized instruction, quality instruments and accessories, and a longstanding commitment to supporting music education in the community, Music & Arts continues to inspire musicians throughout West Hartford and the surrounding area.



https://stores.musicarts.com/ct/westhartford/music-store-0073.html

The Claypen

997 Farmington Avenue


Looking for a creative way to spend the day? Located at 997 Farmington Avenue in West Hartford Center, The Claypen invites visitors to unleash their creativity through pottery painting, glass fusing, and a variety of hands-on workshops. With projects for all ages and skill levels, the studio is a popular destination for families, friends, date nights, birthday parties, and special events.


For nearly three decades, The Claypen has provided a welcoming space where the community can relax, create, and take home a personalized piece of art they'll treasure for years to come.


 https://www.theclaypen.com/

Hard Hats Meet Hashtags

For photos from the West Hartford Center Project, follow us on Instagram. Stay informed about ongoing work, business highlights, and what’s next for the project!

Stay Informed: Sign Up for Text Alerts

Community members and business owners can opt in to receive SMS text alerts for time-sensitive West Hartford Center Construction Project updates, including traffic impacts and schedule changes. Enroll and stay informed throughout construction.

ATTENTION: Local Businesses - Get the Business Toolkit

Signage to Help Keep Your Business and Customers Informed!

In this Toolkit:

  • Business Rack Cards - Tips
  • Business Placards - Click link below to see customized window and/or cash wrap signage for your industry!

If you need additional copies of outreach materials, such as window signs, or have any questions, please feel free to contact us at CenterConstruction@westhartfordct.gov — we’re happy to assist.

The Retail Validation Program:

A Reduced Rate Employee Parking Option for Your Staff

As construction progresses, we're working to maximize on-street parking for customers and visitors. To help, we encourage employees to use alternative parking options, including the Town Center Parking Garage, which offers reduced rates for retail and restaurant employees working in the Center.


The Town Center Garage rates are far lower than other options! The rates are $4.50 for up to an 8.5-hour shift and $7 for anything over 8.5 hours.


For more information, contact Kristen Gorski, Economic Development Manager, at kristen.gorski@westhartfordct.gov.

Stay Informed and Ahead of the Curve

For the latest updates and important information about the project, visit our project webpage. It’s your go-to resource for all the news, timelines, and tools to help your business navigate the construction period smoothly.

Have questions or feedback? We’re here to help—email us at CenterConstruction@westhartfordct.gov