The Town of West Hartford would like to share an update on ongoing construction activity along Farmington Avenue. We’re pleased to report that the contractor is currently ahead of schedule and plans to begin work in Phase 3. This progress is expected to help accelerate the overall project timeline within that section of Farmington Avenue.
At the same time, Phase 2 work is now anticipated to begin on April 6. This slight adjustment is due to recent design modifications associated with the new mobility hubs.
Below is the updated phasing schedule and list of businesses located within the upcoming work zones.
Phase 2 | April 6 – June 5
Chipotle
Max’s Oyster Bar
Ichiro Hibachi & Sushi
Chase
Phase 3 | March 23 – May 22
Coldwell Banker Realty
Pink Soda
The Elbow Room
Toast West & Spirits
Sevan Jewelers
Café Sofia
SOSS Martial Arts
Hope & Stetson
Ace Hardware
New Grace Nails & Spa
Treva
You will notice some overlap in the proposed schedule for the various phases. This approach is intentional and reflects the use of two construction crews working concurrently. One crew will focus on underground utility improvements, while a second crew will follow with sidewalk and surface restoration work. Using two crews will help accelerate overall construction and reduce the duration of each individual phase.
Please note that the date ranges shown on the schedule are tentative and remain subject to change based on weather, field conditions, and other project-related factors. If the schedule shifts, the phasing plan will be updated and shared as revisions are finalized.
|