As work continues in West Hartford Center, the following construction activities are anticipated along Farmington Avenue over the next two weeks.


June 29 – July 3

Phase 2A/2B

Pending Gerber’s receipt of revised construction drawings

  • Reset bus shelter
  • A&J on site for granite curb installation and flat work
  • ETC on site for light pole removal and conduit work
  • Eversource on site for light disconnect work
  • Install new traffic signage for a one-lane westbound travel lane on Farmington Avenue


Phase 4

  • Install catch basin, complete manhole conversion, and install 12-inch reinforced concrete pipe
  • Provide temporary midblock crosswalk during completion of this work
  • Continue installation of soil cells
  • Begin installation of handholes, conduits, and light pole bases


Phase 5

  • Complete drainage structure and piping work
  • Install handholes and light pole bases
  • Remove existing light bases
  • Install granite curb
  • Fine grade areas in preparation for sidewalk installation
  • Begin surface removal of sidewalk pavers in front of businesses starting June 30, beginning near Jenny Andre and moving east*
  • Form and pour sidewalk in front of businesses*
  • Outreach will notify businesses of the exact concrete pouring schedule once confirmed
  • ETC on site as needed for fixture, conduit, and electrical work


*In preparation for sidewalk pours at business front, Gerber will be removing pavers and placing process aggregate/stone dust walkways for pedestrians.


Please Note: Gerber will not be working on Friday, July 3, in observance of the holiday weekend.


July 6 – July 10

Phase 4

  • Continue surface removal of sidewalk pavers, roadway, and curb
  • Continue drainage structure and piping installation
  • Prepare areas for granite curb installation
  • Prepare areas for sidewalk installation


Phase 5

  • Continue surface removal of sidewalk pavers in front of businesses*
  • Continue forming and pouring sidewalk in front of businesses*
  • Outreach will notify businesses of the exact concrete pouring schedule once confirmed
  • Eversource on site for cabinet disconnect work
  • ETC on site as needed for fixture, conduit, and electrical work


*In preparation for sidewalk pours at business front, Gerber will be removing pavers and placing process aggregate/stone dust walkways for pedestrians.


Pedestrian Access Note

  • In preparation for sidewalk pours at business frontages, Gerber will remove pavers and place process aggregate/stone dust walkways to maintain pedestrian access.


Please note: All activities are weather dependent.

View the updated project phasing plan here to see when construction is expected in each section of Farmington Avenue.

Business Spotlights

From longtime favorites to new neighborhood additions, get to know the businesses that add to West Hartford’s character, charm, and sense of community.

El Santo

970 Farmington Avenue



Located at 970 Farmington Avenue in the heart of West Hartford Center, El Santo brings the vibrant flavors and culture of Mexico City to the community with an elevated yet welcoming dining experience. Featuring authentic Mexican cuisine with a modern twist, the menu offers handcrafted tacos, fresh ceviche, flavorful entrées, and expertly crafted cocktails made with premium tequilas and mezcals.


Whether you're meeting friends for happy hour, enjoying dinner with family, or celebrating a special occasion, El Santo's lively atmosphere, exceptional hospitality, and bold flavors make it a must-visit destination in West Hartford Center.


https://elsantoct.com/

Choupette

993 Farmington Avenue


Located at 993 Farmington Avenue in West Hartford Center, Choupette is a cozy French café offering an authentic taste of France in a welcoming neighborhood setting.


Founded by French native Adil Chokairy, the café specializes in handcrafted sweet and savory crêpes, traditional buckwheat galettes, fresh salads, omelets, pastries, and expertly brewed espresso beverages made with high-quality ingredients. Choupette provides a charming café experience that keeps guests coming back for a little taste of Paris close to home.


https://www.crepeschoupette.com/

Hard Hats Meet Hashtags

For photos from the West Hartford Center Project, follow us on Instagram. Stay informed about ongoing work, business highlights, and what’s next for the project!

Stay Informed: Sign Up for Text Alerts

Community members and business owners can opt in to receive SMS text alerts for time-sensitive West Hartford Center Construction Project updates, including traffic impacts and schedule changes. Enroll and stay informed throughout construction.

ATTENTION: Local Businesses - Get the Business Toolkit

Signage to Help Keep Your Business and Customers Informed!

In this Toolkit:

  • Business Rack Cards - Tips
  • Business Placards - Click link below to see customized window and/or cash wrap signage for your industry!

If you need additional copies of outreach materials, such as window signs, or have any questions, please feel free to contact us at CenterConstruction@westhartfordct.gov — we’re happy to assist.

The Retail Validation Program:

A Reduced Rate Employee Parking Option for Your Staff

As construction progresses, we're working to maximize on-street parking for customers and visitors. To help, we encourage employees to use alternative parking options, including the Town Center Parking Garage, which offers reduced rates for retail and restaurant employees working in the Center.


The Town Center Garage rates are far lower than other options! The rates are $4.50 for up to an 8.5-hour shift and $7 for anything over 8.5 hours.


For more information, contact Kristen Gorski, Economic Development Manager, at kristen.gorski@westhartfordct.gov.

Stay Informed and Ahead of the Curve

For the latest updates and important information about the project, visit our project webpage. It’s your go-to resource for all the news, timelines, and tools to help your business navigate the construction period smoothly.

Have questions or feedback? We’re here to help—email us at CenterConstruction@westhartfordct.gov