Center Infrastructure Improvement Project Newsletter

Two-Week Look-Ahead Schedule

As work continues in West Hartford Center, the following construction activities are anticipated along Farmington Avenue over the next two weeks.


June 1 – June 5

Phase 1

  • Electrical work will continue, including wiring, fixtures, and outlets.


Phase 2

  • Crews are expected to begin removing sidewalk pavers in front of businesses in preparation for upcoming concrete sidewalk work.
  • Impacted businesses will be notified directly once the concrete pour schedule is confirmed.
  • Temporary stone dust walkways will be installed where pavers are removed to help maintain pedestrian access.
  • Crews will begin grading for sidewalks.
  • Preparation for granite curb installation will continue.
  • Installation of handholes and conduits will continue.
  • Storm drainage installation will continue.
  • Electrical/conduit work will take place as needed.


Phase 3

  • Crews are expected to remove pavers near storefronts up to Treva (980 Farmington Avenue).
  • Sidewalk grading will continue.
  • Concrete sidewalk pours are expected to take place.
  • Crews will regrade and install pavers near Dale Street.
  • Paving around the curbline and Dale Street is expected.
  • Dale Street may be temporarily closed at times during the day while work is underway.
  • Tree pits will be filled with topsoil.
  • Electrical/conduit work will take place as needed.
  • Crews will begin removing barrels, fencing, and equipment as areas are completed.
  • Completed areas will be reopened for public use as conditions allow.



June 8 – June 12

Phase 2

  • Crews are expected to continue removing sidewalk pavers in front of businesses in preparation for sidewalk work.
  • Temporary stone dust walkways will be installed where pavers are removed to help maintain pedestrian access.
  • Sidewalk grading will continue.
  • Storm drainage installation will continue.
  • Electrical/conduit work will take place as needed.


Phase 5

  • Equipment and materials will be mobilized to the area.
  • Temporary pedestrian and traffic controls will be set up.
  • Construction fencing will be placed around the active work zone and adjusted as work progresses.
  • Crews are expected to begin removing sidewalk pavers, portions of roadway, and curb.
  • Soil cell installation is expected to begin.
  • Installation of handholes and conduits is expected to begin.


Please note: All activities are weather dependent.

View the updated project phasing plan here to see when construction is expected in each section of Farmington Avenue.

Business Spotlights

From longtime favorites to new neighborhood additions, get to know the businesses that add to West Hartford’s character, charm, and sense of community.

Larsen Ace Hardware

982 Farmington Avenue



For generations, West Hartford residents have relied on Larsen Ace Hardware as their neighborhood destination for home improvement, gardening, DIY projects, and expert advice. Conveniently located in the heart of West Hartford Center, this family-owned business combines the personalized service of a local hardware store with an extensive selection of tools, paint, lawn and garden supplies, outdoor living products, and household essentials.


Beyond its commitment to customer service, Larsen Ace Hardware actively supports community organizations such as Camp Courant and Children's Miracle Network, reflecting its dedication to making a positive impact both inside and outside the store. Whether you're tackling a major project or searching for that one hard-to-find item, the knowledgeable team is always ready to help.


https://www.larsenacehardware.com/

Kimberly Boutique

968 Farmington Avenue


For more than two decades, Kimberly Boutique has been a fashion destination in West Hartford Center, offering a carefully curated collection of women’s apparel, accessories, shoes, and denim. Founded in 2004, the boutique was built on the idea of creating a welcoming shopping experience where every customer receives personalized attention and expert styling guidance.


The team takes pride in helping women find pieces that fit their lifestyle, confidence, and personal style, transforming a shopping trip into a one-on-one styling experience. With its commitment to exceptional service, fashion-forward selections, and strong relationships with longtime customers, Kimberly Boutique continues to be a beloved local business and a staple of the West Hartford Center shopping community.


https://kimberlyboutique.myshopify.com/

Hard Hats Meet Hashtags

Stay connected with what’s happening in the Center as work progresses. Follow us on Instagram for photos, project updates, business spotlights, and more.

Stay Informed: Sign Up for Text Alerts

Community members and business owners can opt in to receive SMS text alerts for time-sensitive West Hartford Center Construction Project updates, including traffic impacts and schedule changes. Enroll and stay informed throughout construction.

ATTENTION: Local Businesses - Get the Business Toolkit

Signage to Help Keep Your Business and Customers Informed!

In this Toolkit:

  • Business Rack Cards - Tips
  • Business Placards - Click link below to see customized window and/or cash wrap signage for your industry!

If you need additional copies of outreach materials, such as window signs, or have any questions, please feel free to contact us at CenterConstruction@westhartfordct.gov — we’re happy to assist.

The Retail Validation Program:

A Reduced Rate Employee Parking Option for Your Staff

As construction progresses, we're working to maximize on-street parking for customers and visitors. To help, we encourage employees to use alternative parking options, including the Town Center Parking Garage, which offers reduced rates for retail and restaurant employees working in the Center.


The Town Center Garage rates are far lower than other options! The rates are $4.50 for up to an 8.5-hour shift and $7 for anything over 8.5 hours.


For more information, contact Kristen Gorski, Economic Development Manager, at kristen.gorski@westhartfordct.gov.

Stay Informed and Ahead of the Curve

For the latest updates and important information about the project, visit our project webpage. It’s your go-to resource for all the news, timelines, and tools to help your business navigate the construction period smoothly.

Have questions or feedback? We’re here to help—email us at CenterConstruction@westhartfordct.gov